Some of these issues may have occurred in LA Metro’s process for implementing improvements to LA Metro’s second busiest bus corridor, Vermont Ave.
From 2011 to 2013, LA Metro studied potential BRT projects, with a 100+ page consultant report identifying Vermont as suitable for a BRT. In 2013, LA Metro’s board directed staff to start advancing plans for a BRT on Vermont.
From 2013 to 2017, LA Metro had meetings and produced a 70+ study concluding that BRT on Vermont was feasible. From 2017 to 2019, LA Metro had more meetings and produced another 70+ study concluding that the future BRT could be converted to rail in the future.
In 2019, LA Metro’s board told staff to advance the Vermont project into environmental review, studying both BRT and rail options.
LA Metro spent a lot of time bidding out the contract to do the impact study for the project (this can take a year or more), and was set to award a contract in 2021 (including putting the approval on the board agenda), but it was withdrawn.
According to LA Metro’s planning department, the impact study was delayed because there was a directive to gather community input before starting the impact study. This involved more consultants and more community meetings.
Now we are in 2022, and the community input activities have been complete. Now the impact study is scheduled to start in Spring 2023 (perhaps taking 2-5 years), with a rail study starting sometime after 2024.
What is most worrisome is that the Vermont project doesn’t struggle with political support, NIMBYism or worries about inequitable outcomes (LA Metro’s other projects have those issues, risking more delays), the long timeline has been entirely due to a process of endless studies.

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with numble

numble Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @numble

Nov 8, 2019
Metro-relevant excerpted comments from Ron Tutor, CEO of Metro’s largest contractor, Tutor Perini from Q3 Earnings Call on 11/6/2019. Full transcript at fool.com/earnings/call-…

- Purple Line status update: tunneling on both Sections 2 and 3 expected to occur in 2020
- They have won 3 Metro contracts for $3 billion, expect to be awarded a 4th contract for $440 million
- They will bid on WSAB, ESFV and Sepulveda Lines, and LAX Metro Connector station contract ($13 billion total)
- LA Metro projects expected to be the backbone of their business
- He says they basically get to dictate contractor-friendly terms due to lack of competitors
- they declined an invitation to bid on a transit project in Canada as they focus on CA and NY
- If there are literally no competition, they will ask for a higher price
Read 5 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Don't want to be a Premium member but still want to support us?

Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal

Or Donate anonymously using crypto!

Ethereum

0xfe58350B80634f60Fa6Dc149a72b4DFbc17D341E copy

Bitcoin

3ATGMxNzCUFzxpMCHL5sWSt4DVtS8UqXpi copy

Thank you for your support!

Follow Us!

:(