Joe LaRusso 🔌 🕳🐇 Profile picture
Apr 16 37 tweets 8 min read Read on X
🧵
I’m not sticker-shocked at the $1.5B price tag of @EversourceMA’s GCEP project, considering the miles of work in public roadways & the drilling under the river to submerge the cable, build & retrofit substations, etc.

No, what galls me & should gall everyone…

#mapoli
…is that in its MA DPU dockets seeking approval of their two proposed LNG supply contracts with Everett Marine Terminal (EMT) Eversource said that alternatives to the contracts —physical upgrades to its gas distribution system to enhance system safety and reliability would,…
…well, take a *lot* of time and work.

Specifically, Eversource’s expert testified that “an internal distribution betterment option with expansion of the LNG vaporization capacity would be similar in costs to the Proposed Agreement, and, given the scope of the required…
…construction, needed permits and other considerations it could take several years to complete.”

Construction. Permits. Years to complete. Oh my!

But years to complete? Seriously? After all of the years that Eversource squandered after it first knew that EMT—the facility it…
…says it relies on to provide gas supply on peak design days and needs to maintain gas pressures and gas system reliability—might be going away? Really?

Let’s account for the years that Eversource squandered after it knew that EMT was in danger of being shuttered. Let’s work…
…our way backward in time.

October 2021
Eversource releases an RFP for gas supply for the winter 2024/25 (i.e. next winter). Winter 2024/25 is significant because it will be the first winter after Mystic Generating Station closes. Mystic, which is adjacent to EMT & is fueled…
…by its LNG, is EMT’s biggest customer and takes ~ 75-80% of EMT’s “sendout.” Mystic is operating on a “cost of service” (COS) agreement approved by @FERC. Once the COS agreement ends this coming May 31, Mystic will cease operations. Constellation has said that if it can’t…
@FERC …replace the fixed contract revenue that Mystic provided with new fixed contracts, it too will cease operations. Constellation responded to Eversource’s October 2021, RFP and the two companies began negotiating fixed contracts that would allow EMT to keep operating and…
@FERC …allow Eversource to buy gas for winter 2024/25–and every subsequent winter through 2029/30–from EMT. @nationalgridus and @Unitil negotiated similar contracts with Constellation, and it is these four contracts that are currently before the DPU pending approval.
@FERC @nationalgridus @Unitil Next stop going backward in time?

December 2018
FERC approves the first Mystic COS agreement to keep it operating so that ISO New England can plan for the closure of the largest fossil fuel plant in New England.

That is, more than five years ago everyone, including…
@FERC @nationalgridus @Unitil …Eversource, knew that Mystic was on borrowed time and would soon be closing. And because Eversource is as sophisticated a participant in gas markets as any, it knew what the implications would be for EMT if Mystic closed. Eversource knew that if Mystic closed, EMT would…
@FERC @nationalgridus @Unitil …be in jeopardy. More than five years ago.

But let’s go back in time a little further still…

March 29, 2018
Six years ago Mystic’s owner announced that it would retire the power plant. Six years ago Eversource knew Mystic’s days were numbered, and that EMT’s days were…
@FERC @nationalgridus @Unitil …potentially numbered as well.

Knowing that it relied on EMT for gas supply during peak demand events (think Polar Vortex), and on certain days to maintain gas distribution system pressures and reliability, what did Eversource do six years ago when Mystic’s owner announced it…
@FERC @nationalgridus @Unitil …intended to close Mystic and, in essence, threw a grenade into the region’s electricity and gas markets? Nothing. Eversource did nothing. Neither did National Grid or Unitil.

It wasn’t until almost three years later, when Eversource released its RFP for winter 2023/24 gas…
@FERC @nationalgridus @Unitil …supply, that Eversource provided any indication that it was planning for EMT’s possible closure. But Eversource’s planning relied exclusively on a strategy to keep EMT open by providing EMT with the fixed contract revenue it needs to sustain operations. That is, …
@FERC @nationalgridus @Unitil …Eversource’s exclusive strategy was—together with National Grid and Unitil—to step into Mystic’s shoes as EMT’s counterparty for the fixed revenue contracts EMT needed to remain open. Apparently, during those six years Eversource never seriously considered upgrading its own…
@FERC @nationalgridus @Unitil …gas distribution system in anticipation of EMT’s possible closure. It never considered “an internal distribution betterment option,” as its expert testified because, you know, Construction. Permits. Years to complete.

This is a utility which, on the electricity side of the…
@FERC @nationalgridus @Unitil …house is implementing a project as vast, & complex, & costly as GCEP (), and on the gas side of the house is implementing a project as vast, & complex, & costly as the pipe replacement GSEP project ()eversource.com/content/reside…
mass.gov/doc/eversource…
@FERC @nationalgridus @Unitil In short, at some point during the last six years Eversource decided not to upgrade its own gas distribution assets to prepare for EMT’s possible closure, but decided instead to execute contracts that require it to rely on Constellation’s asset, EMT. Moreover, the four…
@FERC @nationalgridus @Unitil …contracts ain’t cheap: they’re estimated to cost almost one billion dollars over the six years they’ll be in place. Which brings us to the six year terms of the contracts. Why six years? That was a question that the Attorney General asked in the DPU dockets. The answer? Six…
@FERC @nationalgridus @Unitil …years is enough time to build new gas transmission capacity—new pipelines—into the region so that the utilities would no longer need to rely on EMT. There’s but one gas transmission project out there that’s been proposed: @Enbridge’s Project Maple. static1.squarespace.com/static/56afc3b…
@FERC @nationalgridus @Unitil @Enbridge Consruction. Permits. Six years to complete. If it’s all in service of building a new gas pipeline into the region, then those daunting challenges seem suddenly surmountable.

It should be clear that, if you want to picture how Eversource, National Grid, & Unitil see New…
@FERC @nationalgridus @Unitil @Enbridge …England’s energy future, you have to imagine that the future will be gas: gas now, gas for the foreseeable future, gas, just gas.

In light of the decarbonization mandated by the Commonwealth’s Global Warming Solutions Act and the Order issued by the DPU in its Future of Gas…
@FERC @nationalgridus @Unitil @Enbridge …docket (which no longer allows cost recovery for gas infrastructure without proof that non-gas alternatives were considered, or for the promotion of natural gas expansion), the gas now, gas for the foreseeable future, gas, just gas mindset of Eversource, National Grid, & …
@FERC @nationalgridus @Unitil @Enbridge …Unitil is not only out of step with reality, it is out of step with the Commonwealth’s legal requirements.

But that is not what galls me and should gall everyone else. No, what galls me is that, notwithstanding how long they’ve known EMT was in jeopardy of closing… Image
@FERC @nationalgridus @Unitil @Enbridge …—six years—and all they could have done to prepare for its eventual closure, it wasn’t until last February 12 that Eversource, National Grid, & Unitil opened their dockets to have their contracts with Constellation approved. Moreover, it…
@FERC @nationalgridus @Unitil @Enbridge …is impossible not to discern the importance the utilities attach to themselves for having delivered—at the 11th hour—the contracts they say will prevent mid-winter gas outages that could leave untold thousands of Mass. residents freezing in the cold for weeks on end. “Look…
@FERC @nationalgridus @Unitil @Enbridge …at us! We’re heroes! We come bearing the solution that will vouchsafe the reliability of the gas distribution system and keep the wolf of gas outages away from each and every door!”

As if.
@FERC @nationalgridus @Unitil @Enbridge No, Eversource, National Grid, and Unitil are not to be congratulated for coming up with a scheme to keep EMT open when it’s by no means clear that the region needs to continue relying on it. (Gas use for electricity generation is plateauing in New England; residential gas use…
@FERC @nationalgridus @Unitil @Enbridge …for heating is or soon will be plateauing.)

Eversource, National Grid, and Unitil should in fact be contrite. Contrite for doing nothing during the last six years, even though they knew that long ago the risks that EMT’s closure posed to gas distribution system…
@FERC @nationalgridus @Unitil @Enbridge …reliability. Contrite for not upgrading their own distribution system—their own asset—to enhance reliability, opting instead to rely entirely on Constellation’s. Contrite for dropping this hot potato in the DPU’s lap in early February with the admonition that the contracts…
@FERC @nationalgridus @Unitil @Enbridge …had to be approved by May 1, or else.

Or else. If the contracts are not approved by May 1 the entire transaction will crater. EMT will close. There will be no way to maintain gas distribution system reliability and safety.

Or else.
@FERC @nationalgridus @Unitil @Enbridge So if the DPU finds that it lacks the legal authority to approve the contracts given the structure of the transaction (and there is SJC precedent that suggests this might be the case), or if the Attorney General or some other party with standing successfully appeals an…
@FERC @nationalgridus @Unitil @Enbridge …order of the DPU approving the contracts, the utilities would have us believe they, and not the utilities, would be responsible for the catastrophe of a mid-winter gas outage.

No. No, responsibility for any gas outage that might occur, with or without EMT—whether because…
@FERC @nationalgridus @Unitil @Enbridge …the DPU declines to approve the contracts, or some litigant successfully appeals their approval—will squarely rest on the shoulders of the utilities. They knew. They had sufficient time. They did nothing to upgrade their assets in the face of a known risk to reliability. They…
@FERC @nationalgridus @Unitil @Enbridge …backed Mass. officials and residents into a corner by waiting until February of this year to approve the solution they preferred to pursue.

The utilities should be contrite because it is the people of Massachusetts that gave them regulated monopolies to provide safe,…
@FERC @nationalgridus @Unitil @Enbridge …reliable, and affordable gas service, and there is *every* indication that, in this case, they failed to meet their obligations under that compact.

That’s what galls me.

###

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with Joe LaRusso 🔌 🕳🐇

Joe LaRusso 🔌 🕳🐇 Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @jglarusso

Mar 28
🧵
In 4 dockets @Mass_DPU, Eversource, National Grid & Unitil are seeking approval of contracts w/ @ConstellationEG, owner of Everett Marine LNG Terminal (EMT). The contracts would allow the threatened EMT to remain open.

The utilities have unsheathed their long knives.

#mapoli
The 4 contracts would provide Constellation’s EMT with a source of fixed revenue that would replace its current source of fixed revenue, Mystic Generating Station (MGS), which is scheduled to close for good in 66 days, on May 31.

EMT needs a source of *fixed* revenue…
…not only to pay its operating costs, but also to have a means to pay for forward contracts it will have execute with LNG suppliers to schedule LNG shipments for next winter 2024/25.

The utilities state in the dockets that the 4 contracts must be finalized by June 1 in order…
Read 25 tweets
Feb 14
🧵

There it is folks, Everett LNG Marine Terminal (EMT) WON’T be closing, at least not for 6 more years.

No, it’s not dead yet, but now it will be up to gas ratepayers to pay to keep it on life support.

Is it worth postponing the inevitable?

#mapoli

commonwealthbeacon.org/energy/utiliti…
Before answering that question it’s worth taking a quick trip in the WABAC machine to remind ourselves about the circumstances that placed EMT in peril in the first place. Then we’ll talk about LNG tank congestion charges, and Project Maple too.

I can already see your eyes…
…rolling to the backs of your heads, but bear with me. I’ll do my utmost to make it worthwhile.

1. HOW WE GOT HERE (…Ask not for whom the bell tolls, it tolls for EMT.)

In March 2018 the owner of Mystic Generating Station (MGS), New England’s largest gas power plant, …
Read 50 tweets
Nov 22, 2023
In a very real sense VPPs are not just a “thing,” they *are* the thing: they are the consummation of the transition to a clean energy electric grid.

Whereas before—and for the most part still—electricity customers are passive recipients of power delivered by a wire tethered…
…to their homes and businesses, VPPs make it possible for those customers to transact to give services back to the grid. What was formerly a one-way street is now, via VPPs, a two way street, with thousands, and soon millions, of individual customers helping to …
… maintain the reliability and affordability of the grid.

How? In truth every single home/business is a potential grid “asset” simply by virtue of having garden variety “load”: appliances and lighting that consume grid-provided electricity. That load has value for grid…
Read 15 tweets
Sep 20, 2023
.@Enbridge is planning an expansion of its Algonquin Gas Transmission Pipeline (AGTP): Project Maple. On 9/12 Enbridge announced an "open season" for the expansion project. infopost.enbridge.com/GotoLINK/GetLI…
FERC has jurisdiction over interstate natural gas pipelines. For existing pipelines like AGTP to be expanded, or for new pipelines to be built, FERC must find that there is a need for the project and that it will serve the public interest. The “open season” process is part of...
...documenting need (demand) for Project Maple as a prerequisite for obtaining FERC approval to proceed with it. It’s early, early days for Project Maple.

There have been two previous AGTP expansion projects: the Atlantic Bridge project and the Algonquin Incremental...
Read 9 tweets
Aug 31, 2023
On August 15th the Massachusetts DPU issued an Order opening an Investigation into municipal aggregation (docket no. 23-67). The docket will no doubt be enormously significant for the 177 Mass. cities/towns that have implemented…



#mapolifileservice.eea.comacloud.net/FileService.Ap…
…aggregations, as well as most of the remaining 174 Mass. cities/towns that have yet to implement aggregations, but that may do so in the future. (Exception: cities/towns w/municipal light departments may *not* form aggregations.)
Per the DPU, the purpose of its Investigation is “(1) to establish guidelines governing the filing requirements and the process by which the [DPU] reviews and evaluates municipal aggregation plans, as well as the rules governing operation of a municipal aggregation program…
Read 30 tweets
Jan 11, 2023
🧵 It’s disheartening to continue reading stories like today’s @BostonGlobe piece by @andrewnbrinkman that include false statements like this: “Because of supply constraints tied to pipeline capacity into New England, frigid temperatures caused natural gas prices to surge, []…
…making oil a ‘more economical’ choice when conditions are poor.”

We know the statement is false because of a decision @isonewengland made way back in the spring-summer while preparing for this winter. In years past ISO-NE implemented a Winter Reliability Program (WRP) that…
…paid dual-fuel generators to buy & store oil on-site. ISO-NE’s concern was that, in the absence of WRP payments, dual-fuel generators wouldn’t incur the expense of buying oil they might not need to run. But last spring/summer ISO-NE realized that it wouldn’t need to make WRP…
Read 11 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Don't want to be a Premium member but still want to support us?

Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal

Or Donate anonymously using crypto!

Ethereum

0xfe58350B80634f60Fa6Dc149a72b4DFbc17D341E copy

Bitcoin

3ATGMxNzCUFzxpMCHL5sWSt4DVtS8UqXpi copy

Thank you for your support!

Follow Us!

:(