#Demystifying #EIANotification Process (Cont)
Today we cover d final bit of d #Process namely
#SCHEDULE which lists d #projects/activities for which #Prior #EC is mandatory.

#EIA1994 carried a list of 32 projects / activities that required environmental clearance (EC) from+
d Central government. An exception was made in case of few kinds of Thermal power projects (eg captive power projects) which could seek EC from d respective State governments.

In #EIA2006 Thirty nine (39) projects or processes were listed in d #Schedule to d Notification.
These were categorized into following 8 different categories. Each was further sub divided into several others. A note on “#General” Conditions was appended to d #Schedule.
1.Mining, extraction of natural resources & power generation
2.Primary Processing
Read 15 tweets
#Demystifying #EIANotification Part III (Cont)
Today we deal with #Appraisal.
#Expert appraisal of a #ProjectProposal by d #Competent Authority (CA) to determine whether a Project deserves to b granted/rejected an #EnvironmentClearance (EC) is essence of #EIANotification.
The @moefcc as d CA was conscious of d fact since #EIA1994 that it wud in-house not possess necessary expertise to assess d different kinds of #projectproposals that come its way & hence provided that:

"The reports submitted with d application shall be evaluated+
& assessed by d Impact Assessment Agency, and if deemed necessary it may consult a committee of Experts , having a composition as specified in Schedule-III of this Notification."
Later #EIA2006Notification created standing committee of Experts to be called as+
Read 18 tweets
#Demystifying #EIANotification Part II
PURPOSE
Part I was abt #Evolution. This is abt #Purpose.
Purpose of #EIANotification is to properly assess in #advance d likely environmental impacts of planned developmental ‘#projects’ so that informed decisions cud be made well in time +
& then a #competent #authority (CA) could either accord or decline an EC (#EnvironmentClearance) to a project proponent (PP).
Presumption of course is that d CA is bound by its constitutional duty under Article 48A & d preamble of EPA1986 to ‘protect’ & ‘improve’ d environment.
Project
#project’ has been defined as “expansion or modernization of any activity (if pollution load is to exceed the existing one) or new project listed in Schedule I to d notification.”
#Competent #Authority (CA)
In #EIA1994Notification d CA was d Central Government +
Read 20 tweets

Related hashtags

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3.00/month or $30.00/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!