Discover and read the best of Twitter Threads about #fourmorewithaa

Most recents (1)

As promised, the Administration of Mallam AbdulRahman AbdulRazaq is still on track towards the completion of the General Babatunde Idiagbon Flyover Bridge

#Isenlo #AAJourneySoFar #FourMoreWithAA

#Thread ImageImageImageImage
We have doubled up our effort on schedule. Work is going as planned and the scheduled date for completion remain December 23, 2022.

Below is the breakdown of construction activities since the commencement of the project;
*Completed Activities*
• Piles 100% completed
•Pile caps 100% completed
•Piers 100% completed
•Precast Beams 100% completed
•Concrete casing protection for NNPC pipeline 100% completed

*Ongoing Activities for the week*
• Final Reinforcement for Abutment wall 1 (80%)
Read 6 tweets

Related hashtags

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3.00/month or $30.00/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!