CCECC Nig. Ltd., upon work #resumption in May from the lockdown, made efforts to regain all lost time in order to complete all lanes at the section covering Trade-Fair to LASU on the Lagos–Badagry Expressway project at a constrained time frame.@FMWHNIG @LSPWC_Official @LASGWorks
Over 2.7km of construction has been completed on the service lane and 2.3km on the toll lane–Badagry bound. The installation of drains, kerbs, barriers, etc. is ongoing. The proposed diversion at Iyana-Iba is at the stone dust filling, spreading, and compaction stage.
At the Iyana-Iba interchange – Lagos bound side, construction is progressing in preparation for the erection of piers. The trimming of piles and the construction of pile caps are major points of concentration and this part of the project is almost completed.
Read 5 tweets

Related hashtags

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3.00/month or $30.00/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!