Rather interestingly the 'consent to locate a mobile installation' for the #i3E Liberator A3 appraisal well, has been updated as of yesterday, with an anticipated start date of 31st Oct.

2/2
More interestingly, said #I3E permit was updated 1 day after the Oil Discharge Permit variation to the Serenity well, was itself updated.

Meaning whatever is happening at Serenity will soon be complete, and the A3 drill location is now known.

In one fowl swoop we have a deadline for the Serenity well, and we know that A3 is going to happen, and happen soon.

The #I3E Oil Discharge Permit for Serenity remains outstanding. I would think it won't be for very long.

Correction one fell swoop. . .

A 31st Oct location date for the A3 appraisal well would place #I3E at 78 days into their drill programme, and Serenity total drill programme at just 31 days.

A3 appraisal programme rig mobilise 3.5 days. Total planned 40 days.

Potential to be complete in total of 109 days.