Latest update on Eskom BESS Project tender, is that it is planned for release in Q1 2020.
More importantly, the 200MW phase 1 project, made up entirely of battery storage and valued at $485m, has had its completion date revised to June 2021.
Game on #BMN #vanadium
25th Sept 2019
"The only ministry that has not yet signed off is the Department of Public Enterprises, Moyo added."
"without committing to a launch date for the solicitation. “It’s imminent,” he said."
greentechmedia.com/articles/read/…
According to latest update from the World Bank, Eskom BESS Project received its final government approval from the Dept of Public Enterprises on 21st Nov 2019.
No more political barriers exist. So it's now purely about the Eskom finalising the tender.
Its truly imminent #BMN
And here's the evidence for all to read and make their own minds up themselves. #BMN #vanadium #EnergyStorage
documents.worldbank.org/curated/en/945…
"He (Prince Moyo of Eskom) noted that bids will be evaluated on a total cost of ownership basis. Eskom is also looking for performance guarantees over 20 years and will be imposing penalties for noncompliance."
#BMN #vanadium #EnergyStorage
esi-africa.com/industry-secto…