ONGOING: The Lekki Regional Road Project will serve as an alternative to the Eti-Osa Epe Expressway as promised by Governor @jidesanwoolu, it will decongest traffic within the Lekki region, provide access to VGC, Ikate, Ikota, Ajiran, Chevron etc

#SanwoProjects
The Special Adviser to Gov @jidesanwoolu on Works and Infrastructure, Mrs Aramide Adeyoye during inspection of the project on Thursday, 23rd September 2021 said Lekki Sub-region is the new economic centre of Lagos with huge amounts invested in the region.
REGIONAL ROAD PROJECT DETAILS:

- 8.75km road
- 500m bridge
- 251m interchange
- 50m bicycle lane
- and an adjoining 500m road
- Completion Status: 23.56 % (Sep 2021)

ROUTE: From VGC junction to Freedom Way

Contractor: Messrs HITEC Construction Company Ltd.
“The contractor is on site and they have done a lot of work behind the scene, pilling works for the pedestrian bridges are completed and the bridges are already in place while a lot of sand filling dredging on the road alignment has been achieved” - Engr Mrs Aramide Adeyoye
VIDEO: Several large pilling rings were ready and the pile reinforcement cages to be used in foundation works for bridge signals the commencement of the bride components of the project.

Governor @jidesanwoolu promised this major infrastructure & showing workings immediately. 🚧
The Special Adviser to the Governor of Lagos State on Works and Infrastructure, Engr Mrs Aramide Adeyoye says Governor @jidesanwoolu promised this project and delivering it, she says this regional road will serve as an alternative to Lekki Expressway.
Engr Mrs Aramide Adeyoye said the project would further open up the Lekki area to serve as alternative route and link to several communities and industrial areas.
She said Governor @jidesanwoolu was committed to massive infrastructure delivery.
Mr Danny Abboud, Managing Director, Hitech Construction Company Ltd said that the firm had been working round the clock since they moved to site to deliver the project on schedule.
Abboud said sand was being dredged directly from the Lagos Lagos to ease construction works on the Lekki Regional Road which spans from Victoria Garden City to connect Freedom Way at Lekki Scheme.
The project which was awarded in May, 2020 but construction began in August, 2020 was billed nfor completion in 22 Months, that is June, 2022.

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with The Greater Lagos Project

The Greater Lagos Project Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @GreaterLagosNG

Dec 14, 2022
PRESS STATEMENT

Obaigbena lies again without shame as he manufactures alternate reality

#Obiagbena
#AriseTV

@ARISEtv Image
Ordinarily, we consider it beneath us as well-bred media professionals to continue to engage in public spat with Mr. Nduka Obaigbena, a congenital blackmailer and hustler, especially in deference to ceasefire calls by well-meaning leaders and elders.
The interventions followed our statement on Monday entitled “Obaigbena and His THISDAY/ARISE News’ Hypocritical Grandstanding On Public Morality”.
Read 55 tweets
Jan 17, 2022
The Time Has Come To Choose Wisely
By Senator Kashim Shettima (@KashimSM)

I stand here today honoured by the burden of expectations upon me and, more tellingly, strengthened by the convictions of the patriots with us in this journey to make history.

#TheBATSupportSummit
We are brought together by a forest of ideas, but what defines us and sets us apart from other political groups is this collective realisation that the future of this country rests on the choice of a unifying leader; ..
..a leader who panders to neither ethnic nor religious agenda, and one who isn’t bound by toxic regional solidarity and yet known for a track record of outstanding leadership.
Read 39 tweets
Dec 23, 2021
ILLEGAL ENFORCEMENT OF JUDGMENT BY SHANGISHA LANDLORDS ASSOCIATION INRE SC/112/2002 BETWEEN MILITARY GOVERNOR OF LAGOS STATE & ORS. V. CHIEF ADEBAYO ADEYIGA & ORS.

#Magodo
i. On the 21st of December, 2021, it was reported through social media platforms that the Shangisha Landlords Association with stern looking Policemen took over Magodo Area of Lagos State in purported execution of a Supreme Court judgment.
ii. It is a known fact that judgment was delivered in 2012 by the Supreme Court in Military Governor of Lagos State & Ors. Vs. Adebayo Adeyiga & Ors in Appeal No: SC/112/2002….
Read 27 tweets
Dec 20, 2021
UPDATE: Governor of Lagos State, Mr Babajide Olusola Sanwo-Olu @jidesanwoolu today commissioned a Network of 9 roads with bridge within the Soluyi Community in Kosofe Local Government.

#SanwoIsWorking
#ForAGreaterLagos ImageImageImageImage
The Contract award for the Construction of Network of Roads within Soluyi Community in Kosofe Local Government Area was awarded to Messrs Xenon Construction Limited in September, 2017. The project consists of a network of nine (9) roads. ImageImageImageImage
The roads: Aderemi Akeju street with deck-on-pile bridge, Okun street, Femi Kufo street, Brown Street, Adegbenro street, Ganiyat Dawodu streets, Yetunde Brown street, Anipole street, Sosanya streets. ImageImageImageImage
Read 8 tweets
Dec 11, 2021
UPDATE: The 32-metric tons per hour Rice Mill being constructed by Lagos State Government in Imota area of Ikorodu division will start operations before end of first quarter in 2022. Governor @jidesanwoolu gave this assurance after touring the project site on Friday.
@jidesanwoolu said the facility would be subjected to a pre-production test run before the end of first quarter next year, after which the full production capacity would be activated rice production.
Two years after his first visit, the Governor went on an on-the-spot assessment of the biggest agro project being undertaken by a sub-national Government. He was accompanied by Commissioner for Agriculture, Ms. Abisola Olusanya, and members of the State cabinet.
Read 14 tweets
Dec 11, 2021
Lagos State Government and the U.S. Agency for International Development (@USAID) have signed a Memorandum of Understanding (MOU) to improve access to safe water, sanitation, and hygiene (WASH) services. 

#ForAGreaterLagos

@jidesanwoolu @OlalereOdusote
The Honourable Commissioner, Ministry of Energy and Mineral Resources, Mr. @OlalereOdusote, who is Chairman of the Ad-hoc “Lagos State Water Corporation - ExCo Strategic Review Committee”, said the MOU will ultimately enhance urban water service delivery in Lagos State, ..
… through infrastructure improvement, accountability, strengthened regulatory oversight of the Lagos State Water Regulatory Commission, as well as governance, financial and technical capabilities of public and private sector stakeholders.
Read 11 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Don't want to be a Premium member but still want to support us?

Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal

Or Donate anonymously using crypto!

Ethereum

0xfe58350B80634f60Fa6Dc149a72b4DFbc17D341E copy

Bitcoin

3ATGMxNzCUFzxpMCHL5sWSt4DVtS8UqXpi copy

Thank you for your support!

Follow Us!

:(