#NASA#NAC#HEO - Taken objectives and broken them down into 4 categories, form those objectives we're creating an architecture. with our workforce, international partners, industry and academic partners
#NASA#NAC#HEO - Have to start from the right, what we have done is execute this process, has to actually match from the execution form the left
#NASA#NAC#HEO - Have taken all of the objectives and mapped them.
#NASA#NAC#HEO - It's the first time in the agency we did a concept review, and get feedback on what was created, this will be the first of an annual cadence as we move forward. Want to make sure all directorates have a feed-forward t make sure budget aligns
#NASA#NAC#HEO - Segments of the architecture that are being developed.
#NASA#NAC#HEO - Trying to build that bridge between what we need for Mars, creating sub- architectures, so we can have something that we can build upon for a Mars mission. Want to build a flexible Architecture.
#NASA#NAC#HEO - Hale : How do you balance the moon and Mars? A: The intention is to go to the moon and stay and do sustained lunar exploration but NOT at the expense of Mars. Architecture review will be an annual cadence to make certain we're meeting them,
#NASA#NAC#HEO - Elements required for the human return missions for the lunar surface. Within initial return element is the Gateway, HLS, and the Suits. Not just ESMD
#NASA#NAC#HEO - The process of architecting from the right doesn't leave out what it's in the middle. We need to know how to explore on MArs; we can only learn how to operate on a celestial body by going to one; the closest one is the Moon. Will evolve through different phases.
#NASA#NAC#HEO - This IS notional as to what these things look like.
#NASA#NAC#HEO - Some of the products that are being generated along with white papers that were created at the request of @Astro_Pam, these address the "why" of key elements.
#NASA#NAC#HEO - Opportunities for Collaboration: There are many opportunities for industry, academia, and our international partners to work with us, expect this list ti ebb and flow as we move along. Korener, being asked ISRU said we're talking with the industry
#NASA#NAC#HEO#TIE _ Why nuclear power and propulsion: The system is well suited for space exploration activities and does share an interest in commercial space.
#NASA#NAC#HEO#TIE - Surface power strategy, want to deliver a qualified flight demo in 2030 and want to transition technology to industry. Looking at a 40Kw scalable system at first. want system to be placed at different lunar surface sites and a 10 year lifetime
#NASA#NAC#HEO#TIE Why develop ISRU Can increase safety for the crew and has direct applications here on Earth. Planetary preservation is paramount
#NASA#NAC#HEO#TIE - ISRU is one of the 6 points of extreme environmental extreme access, dust mitigation, and unique aspects to each one of these points want to make sure we're driving these processes to mitigate risk.
#NASA#NAC#HEO - We have 3 points as described in the chart Develop tech not only for human and robotic exploration but tech that drives the expanding space economy.
#NASA#NAC#HEO - QR code for the strategy 63 top-level objectives developed as a cross-agency activity
#NASA#NAC#HEO - Going over the plan for the #Artemis1 mission. Was a successful mission design
#NASA#NAC#HEO - Amit Kshatriya - What I was really thinking about were all about the US businesses that put thier hands on that hardware, sometimes "Mom & Pop" shops. Just how many of them contributed to the success.
#NASA#NAC#HEO - Jim Free, we want to get on pace to launch every year, that will be a challenge to ac hive without the budget to go with it. Will work closely with the Centers, will have great collaboration but will also be a time when we need to talk stuff though
#NASA#NAC#HEO - Want a sustained presence meaning a robotic presence on the Moon when we don't have crew present
#NASA#NAC#HEO Free: Were going to transition program to operations; Agency decided NOT to do that, so a new organization had to be established