Aidan Morrison Profile picture
Researching energy and defence. Physics and data science background. Happy getting into the weeds.
2 subscribers
Feb 5 19 tweets 7 min read
Not a great day for NSW electricity prices.

Some boffins on LkdIn are scratching their heads over this.

I have a theory. Helluva storyif true.

TLDR: Pure chaos.

Originating over 2000km away on the border between South Australia and Vic.

Tell me where I'm wrong. 1/ Image At 1:50pm, SA is soaked in rooftop solar. They're curtailing excess wind and grid solar. Prices are consistently negative, and dip here to -$200. They run a slither of gas for system security, but weirdly, they're importing nearly 400MW throughout from Victoria. 2/ Image
Jan 21 18 tweets 9 min read
Yesterday, Origin announced they would extend Eraring. No new subsidies. Their own commercial decision.

On 23 December @aergovau, quashed a dispute lodged by @cisoz in a regulatory process, on the basis that extending Eraring beyond 2027 was not "commercially feasible".

As a result, Transgrid has got in-principle access to ~6bn dollars of funding to procure system security services currently provided (at little or no cost) by coal plants, like Eraring.

NSW consumers will have to pay for that.

And all the modelling they used to justify their schedule of rapidly procuring synchronous condensers and grid-forming batteries is based around Eraring closing in 2027.

The essence of one of our main grounds of dispute was that they should consider the possibility that coal would be extended. That might be a lower-cost way of meeting the need?

Impossible, argues Transgrid. Apparently, since no coal power station had knocked down their door to express an interest in remaining open, it was safely discarded as being commercially infeasible.

Nevermind the fact that contemplating paying generators extra to modify their plant, or run their plant for extended hours, was very much the purpose of this whole application, and heavily relied upon for gas in the proposed solutions.

Nevermind the fact that Origin had secured an agreement with the NSW government that gave them the option to operate up to 2029, when NSW only offered underwriting to 2027. In Transgrid and AER's eyes, that doesn't demonstrate interest.

And the Regulator, who should be looking out for consumer interests by testing and challenging proponent assumptions, is just fine with all this.

Today, we can see this for what it is.

This is gaslighting, perhaps more brazen than ever seen before.

Our instincts, supported by every scrap of evidence one could hope to find digest (company profits, deals with NSW, energy prices, capture prices, previous closure dates etc etc) suggested it was commercially feasible to extend.

And yet the authorities, even when challenged, forbade such a contention. "no credible option".

And we now have exactly what they said was not credible come to pass. Consumers have a right to be furious. 1/Image This story was briefly mentioned in today's Australian. But it requires a little more.

Note that the regulator declined to comment.
2/

theaustralian.com.au/business/renew…Image
Image
Jan 12 8 tweets 4 min read
Saturday was very hot in Sydney, over 40 degrees for much of the day.

And as the sun set, it was still hot.
Prices spiked to over $10,000/MWh, and stayed there for nearly an hour.

A short thread on what really happened, and what it means for the renewables transition. 1/ Image Now it's worth noting that at 6:20pm, this spike was still forecast. But it wasn't forecast to endure for 10 price intervals. As it happened, the peak grid demand was slowly falling (middle column in post above), but not as fast as that available (right column) was. 2/ Image
Dec 11, 2025 21 tweets 8 min read
The ISP has an interesting walk-back on the New England Renewable Energy Zone.

Which, by order of @Matt_KeanMP is declared to be a stonking 8GW of network capacity.

Or... it was. 1/ Image
Image
Image
But a consultation paper that was released just in August, on the generation and storage, outlines reaching 8GW in three separated stages.

The third doesn't have timing allocated? (Will it ever happen?)

And they mention two double-circuit 500KV lines. 2/Image
Dec 8, 2025 21 tweets 9 min read
An update for energy geeks on Sydney Ring South.

This is bad. Last Thursday, the NSW government made it crystal clear that they're entirely reliant on AEMO for assessing the need for Sydney Ring South.

Clean buck-pass. No sign of comprehension, let alone responsibility. 1/ Image
Image
Image
This is bad, because Transgrid has said, plain as day, that they're not happy with AEMO's models.

This needs more attention.

In particular, Central NSW (CNSW) to Sydney, Newcastle, Wollongong (SNW) being modelled as a single link.

This could be a catastrophic flaw. 2/ Image
Dec 5, 2025 35 tweets 14 min read
This report from @the_AEMC dropped yesterday.

The headline this year: prices go up in the medium term under current policy. That's a reversal from last year.

And yet the prescription is for more renewables, and faster electrification.

What gives? Isn't that what we're doing, that seems not to be working?

The explanation for that contradiction took some teasing out. I think it's scandalous.

AEMC's capacity expansion model builds less renewables than last year, and ends up with a tighter wholesale market, because the demand outlook has changed.

And they've lied about how the demand outlook has changed. They've said it was a reduction in electrification demand. Their sources (ESOO) contradict that.

What they really mean is not a reduction in electrification demand, but a reduction in electric fudge-factors they've relied upon in the past to cram renewables into the model without it exploding. Namely "coordinated" consumer storage (batteries you buy, but let the grid control), as well as flexible hydrogen.

And an increase data centre demand, which is flat and inflexible, the complete opposite of how they assumed hydrogen demand would work.

So this report should be admitting a collision of reality with earlier unrealistic assumptions.

Something like "with real-world demand, renewables don't work so great", followed up with calls for more firm capacity to match more realistic demand profiles.

But instead they double-down on their earlier optimism, and just call for the fudge-factors they previously relied upon to be rushed back in, blaming the lack of renewables in their model (which is the symptom of a problem, not the cause of it) for pushing prices up.

This is really incredible. They've inverted the chain of causality that actually flows through their model.

Such a blatant misdirect in the conclusions of the analysis that they've done (some of which, in parts, they made genuine and respectable efforts to improve on over previous versions, and I was tempted to commend) is just appalling. 1/Image Let's start with the conclusion.
They've revised the predicted prices upwards, significantly, throughout the period.

We now have overall price increases.

As a veteran of watching CSIRO adjust its reports year on year, this is... unsurprising, but foreboding. 2/ Image
Dec 5, 2025 10 tweets 5 min read
Ok, I'm working on a thread on how @the_AEMC's latest Residential Electricity Price Trends report.

First, a prelude.

On how the report has become what it is.

We're told now that it "should not be taken as a forecast".

It used to be exactly that. A straight-laced short-run forecast, starting from the firm anchor of a complete financial year.

Now they've made it an "outlook" utterly beholden to government policy aspirations, over the longer run, being successful and achieved. With a bunch of caveats and cautions, and bets both ways split across "price" vs "cost", "system" vs "household", "opex" vs "capex" that make it clear as mud to ordinary people.

And nothing like the crisp reflection of recent reality, with plausible short-term extrapolations, that we previously had.

And this was done at the request essentially of Chris Bowen, or at least the Ministerial Council that he chaired.

Short thread to explain. 1/Image First, here's an excerpt from the latest published terms of reference. Which say, explicitly, that it should be a forecast. Despite that being difficult, their instruction is to try, for 3 years, using the last final year as an anchor. 2/
aemc.gov.au/sites/default/…Image
Nov 26, 2025 46 tweets 20 min read
When a massive 330KV transformer blew up at the Waratah super-battery, I told @SkyNewsAust that this threw the transition into "disarray".

The truth is more complex. Waratah was only ever an expensive band-aid on a self-inflicted bullet wound.

Waratah was the band-aid brain-child of @Matt_KeanMP, the Liberal Energy Minister who launched the NSW Roadmap to transition to renewables, and was determined to see Eraring close in 2025.

But the bullet wound hasn't come about as planned. The Labor government of @ChrisMinnsMP turned the gun away, by delaying the closure of Eraring by at least two years, to 2027.

And now it seems likely that Eraring will be extended until at least 2029.

Which would be 4 out of the 5.5 years that the $700million dollar bandaid was contracted to be in place for. (The Roadmap assumes more satisfying solutions, like major transmission and generation upgrades, will be completed around 2030.)

But wait, there's more. In the rush to implement the "shock-absorber" function that comprises the Waratah band-aid (details to follow) some important transmission lines hundreds of km away were taken out of service for urgent upgrades at an unfortunate time.

These lines being down when Eraring had some unexpected problems in May 2024, and contributed directly to a series of massive price-spikes in NSW that led to the suspension of the electricity market. The wholesale price spikes in that month led to an additional ~800 million in wholesale electricity costs for NSW electricity consumers, and contributed to NSW having the highest wholesale costs for the calendar year of 2024 in the NEM by far.

So I think I was wrong to say that this transformer failure pushed the energy transition into disarray. That implies that the transition was somewhat orderly before that happened.

Actually, the very existence and continuation of the Waratah project tells a story that is borne out of tragedy, to be overcome with fantasy, which soon descends into farce.

The tragedy was climate and carbon rhetoric encouraging Origin to pull forward the scheduled closure to 2025.

The fantasy was thinking a 700MW "shock absorber" battery with 2 hours duration would enable Eraring's 2.8GW of dispatchable capacity to exit as planned in 2025.

And the farce is the ongoing execution, which has done and will do far more damage to consumers already than it could ever realistically have prevented.

This isn't just the "band-aid on a bullet-wound" story.

It's the rush to reach a band-aid, in anticipation of a self-inflicted bullet-wound, where in that rush you turn the gun away for a while, but also slip and fall backwards on an upwards-facing knife. And then keep lurching back to get the bandaid, and recommit to shooting oneself.

Please read and share this. The arrogance and incompetence of those who began and still perpetuate this energy nightmare surprises me more and more every day.
1/

skynews.com.au/australia-news… Where to begin? The official declaration by Matt Kean, using his powers under his signature legislation to 'direct' a priority project to be carried out by Transgrid.

In order to close Eraring by 2025.
That much is black and white. 2/ Image
Image
Nov 20, 2025 20 tweets 10 min read
Five years ago, people said integrating renewables at scale was cheap.

Now? Uhh... not so much.

What happened?

We rolled up our sleeves and got started.

Turns out every earlier estimate was wishful thinking. A hopeful hand-wave at best, and we're being mugged by reality, more and more violently, every month that goes by.

Don't believe me? Check out this 80-page mea culpa for the largest Renewable Energy Zone planned for NSW.

The main trunk-line, the 8GW one that should carry 24 billion dollars worth of generation capacity back to Sydney that we spent years identifying a refined corridor for..

When we thought about how to actually build it, we realised the route was bad. Really bad. So we're going to shift it, like 40km East, and start planning again.

Implications for cost and schedule? All secret. 1/Image
Image
Image
Basically, it was un-buildable. Or rather, the scale of civil works required, on "non-conventional" construction required, like lifting tower segments in place with helicopters, made the cost/complexity/safety too.... whatever. Un-buildable.
This is really bad. 2/ Image
Image
Nov 18, 2025 9 tweets 5 min read
Ok, I know you don't need yet another piece of evidence supporting this thread... But anyway.

In 2024 NSW had a spate of massive high-priced days which resulted in the market being suspended.

A line outage right in this pocket of wind contributed a lot. 1/ Image
Image
Now this isn't the exact same line as is proposed for the Sydney Ring South upgrade. It's actually just upstream, kinda in the thick of the wind pocket.

But it's also just one of three 330KV lines connecting that area to Sydney.

So it indicates the sensitivity. 2/ Image
Nov 17, 2025 10 tweets 5 min read
Last night I stayed up late to write a mega-thread on the terrible mess that is NSW transmission planning.

But I forgot to add the chapter that turns farce into tragedy.

All was foretold.
By the Energy Security Board. But they were ignored. 1/ Image
Image
They wrote a major paper about these problems.

This was when the ESB was comprised just of the heads of AEMO, AER, and the AEMC. The CURRENT heads of these organisations.

They suggested systems that amounted to locational marginal pricing, or LMP. 2/

energy.gov.au/sites/default/…Image
Image
Image
Nov 17, 2025 40 tweets 19 min read
When Jesus said "the first will be last and the last will be first" he wasn't giving instructions on how to build out transmission lines.

And yet... In NSW...

This is the story of Sydney Ring South.

Probably the most urgently needed transmission line. Approved to be... delayed??!

Until? Ummm... sometime... after 2033? We'll kick off the first stage of planning and approvals next year.

Now don't get me wrong, I'm firmly opposed to building excessive transmission to facilitate an enormous build-out of weather-dependent generation that has no hope of providing reliable electricity at anything the like the cost of centralised, thermal generation for baseload.

This isn't a giddyup.
This is exhibit A in an epic cluster....

As it happens, a large chunk of wind energy that is ALREADY BUILT in NSW is stuck in a pocket that often can't reach the Sydney load basin when needed most.

At times, we have gigawatts of electricity flowing in the WRONG DIRECTION, exporting electricity from NSW to Victoria, when their spot price is negative, and ours is very positive because we can't get enough power into Sydney, which drives up costs to consumers.

And, here's the kicker:
This project was specifically requested by Transgrid, @Transgrid_AU (the regulated NSW transmission company) to be made 'actionable' in the 2024 ISP framework, after the consultation draft was published without it, because... reasons... big rush.

The Market Operator, @AEMO_Energy, obliged.

And this year, when the process kicked off in the 2024 ISP was meant to deliver its first major regulatory milestone, Transgrid then asked the Regulator to push the deadline back almost a year.

Buckle up... 1/Image Where to start... How about where I started. The point of intrigue.

A few weeks ago, there was some noteworthy weather. Very hot. So high demand.

Very windy. And mostly sunny. (So high supply) And a forecast price spike.

2/

Nov 7, 2025 15 tweets 6 min read
Oh boy, this is embarrassing. US energy expert completely misreads the Australian news.

This is not the fruits of energy abudnance, but a desperate attempt to head-off an economic disaster that arises from a subsidy-fuelled rush into solar.

Let's correct Jesse's take here. 1/ First, millions of Australian's won't get free power at all.

Nothing is free.

So-called "Free Lunch" plans are already on offer with some retailers in Australia. They are... not that popular.

Because you pay more at dinner. 2/
globirdenergy.com.au/energy-saver/f…Image
Oct 21, 2025 6 tweets 3 min read
Breaking news: @AEMO_Energy suprised again by their absurd assumptions not turning out in reality.

Here's why Virtual Power Plant's (consumers handing control of their batteries to their retailers) don't and won't work at scale, and anyone could see it coming:

1. Retail power prices are around ~30cents/KWh
2. That means the general cost (or opportunity cost) for a VPP to discharge a home battery is over $300/MWh, or more with losses.
3. This means that the all the routine price arbitrage opportunities from wholesale being negative during day, and moderately high (say, a bit over $200/MWh) in evening are eliminated.
4. Spot prices are hard to predict confidently. So a retailer isn't likely to frequently bet on forecast spikes that have a thin margin, like $400 or $500/MWh, incase it doesn't materialise.
5. The remaining arbitrage opportunities are for lucrative FCAS services, or for severely high price events. These are very rare, and quite unpredictable.
6. Retailers can't offer very much reliable benefit to consumers for an ability to capture a rare and unpredictable benefit. So their offers are small, like discounts of $20 or $30 off a bill.
7. Most consumers place some value on the security/sovereignty they get over their energy supply from buying a battery. The value the ability to help themselves above the miserly offer they get to help the grid.
8. VPP uptake stays low.

AEMO's models, of course, abstract away the agent incentive structures of our electricity system. And model the whole 'system' being magically orchestrated in a way that minimises costs. 1/Image This is a massive problem for AEMO, because 'coordinated' (ie VPP) battery storage is the largest part of storage by capacity in their electricity transition blueprint, the Integrated System Plan. Hundreds of billions worth. 2/
Oct 20, 2025 17 tweets 6 min read
This is a super-sophisticated (and brazen) piece of lobbying and propaganda.

The story should be about expensive renewable electricity crushing industry.

But it's been presented as a plan to secure "cheap energy" from renewables.

The cunning. The gall... 1/ Image Who could be behind this deft manoeuvre? The Sunrise Project.

"At the heart of the issue for many manufacturers is getting access to cheap, reliable, RENEWABLE energy."

That's the journo writing. As though it's a thing. Taking the implausible figures as fact. 2/ Image
Oct 16, 2025 12 tweets 5 min read
Remember the headlines about how we're all going to die from the heat due to climate change?

The 444% increase in heat-related deaths made plenty of headlines. The footnotes confirm that heat deaths aren't a thing. It's a big increase on a base of nothing.
Cold is worse. 1/ Image
Image
Take this SMH headline "Like a Mad Max Movie"...
It's no exaggeration to say that the likes of @smh want us to believe an apocalypse is coming. 2/

smh.com.au/environment/cl…
Oct 15, 2025 34 tweets 13 min read
As promised, a more thorough review.

The headline claim is a really disappointing word-squirm, because it shifts costs to expensive capital purchases (which are ignored) to reduce operating costs (bills).

But there are other deep problems with their price analytics. 1/ Firstly, what are they arguing for?

To introduce some explicit carbon pricing, because coal isn't leaving fast enough to reach our carbon emissions targets.

They say that coal is leaving for financial and ages reasons, but too slow. 2/ Image
Oct 9, 2025 15 tweets 5 min read
I missed a crucial footnote.

Remember this drawn-out exchange with @DavidOsmond8 about CSIRO's capacity factors? Post-curtailment or pre-curtailment?

@CSIRO made their method explicitly clear in a previous report, which they reference in the latest.

Let's finish this. 1/ Image And on page 80 of the 2022-23 report we have CSIRO's explanation.

These are historically achieved capacity factors in the NEM.

They explicitly discuss economic and transmission curtailment being reflected in these.

Dave was wrong. 2/ Image
Oct 2, 2025 13 tweets 5 min read
Chris Uhlmann asked the NSW goverment whether they've modelled electricity prices.

And he's found a trove of modelling and analysis.

Which the NSW government has entirely refused to disclose to the public.

They know prices are going UP.
And are hiding it. 1/ Image
Image
This is a recent document... from a serious consultancy, all about "Price impact of coal exit". And some industrial loads.

That would tell us for sure whether the energy transition is working, or whether we still need coal.

REFUSED.
2/ Image
Oct 1, 2025 4 tweets 2 min read
What do farmers actually think about wind farms adjacent to their land?

Take 5 minutes to hear my discussion with Tom and Jen, wool growers who are about to be surrounded by the Navarre project. It’s a bit windy outside, which is why we had the longer chat in the wool shed. But this is on top of Tom’s hill, next to where the turbines will start. Either side of the valley will be covered in turbines.
Sep 26, 2025 36 tweets 13 min read
Round 4 on my latest take on GenCost. 🥊

Dave and I are duking it out on 2 key questions:

1. CSIRO's definition/use of 'capacity factor'. Is it pre-curtailment or post-curtailment?

2. Is Marginal Loss Factor (MLF) a fair representation of transmission losses? Or Average?
🔔 Let's start with capacity factor.

The crux of David's latest reply is in this highlighted quote.

"these capacity factors are not used at all in the modelling of renewable integration costs".

This is correct, and I understand. 2/