Quillan Gornt Profile picture
Enthusiast of natural resources, human resources and the counterrevolutionary forces of progress
Jun 24, 2019 11 tweets 3 min read
$NXE a thread about permitting timeframes for the NexGen Energy Rook I Project, I conclude best case permits by 3Q-2021. This analysis is in response to various uncertainty on when the uranium mine might get permits. ...for example: "... first of all, you don't know when the project will actually get permitted and built. So maybe some will say 2023, 2024, 2025, 2026,
2027, there's all this speculation as to how long the permits will take. Who knows..." -@FootnotesFirst smithweeklyinternational.com/online/Wq36PU9…