As Promised, This Is The Complete Expenditure Breakdown Of N162.5b SUKUK Funds Released For 44 Critical Road Projects Across The Nation's Six Geo-Political Zones. The Intention Behind Delivering This Breakdown Is To Offer Insight For Public Accountability. @TrackaNG

#LONGThread
Zonal Breakdown:

North-Central:
N26.5bn (2020)
143.44 kms (2020)
8 Roads

North-East:
N30.5bn
277.53 kms
8 Roads

North-West:
N26.5bn
227.47 kms
7 Roads

South-West:
N27bn
59.74 kms
6 Roads

South-East:
N26bn
99.45 kms
5 Roads

South-South:
N26bn
121.78 kms
10 Roads
NORTH-CENTRAL BREAKDOWN: EIGHT ROADS

(1) DUALIZATION OF SULEJA-MINNA ROAD PHASE II (KM 40+000 - 101+000) IN NIGER STATE

Contractor: Salini Nigeria Ltd
Contract Sum: N36.2bn
Current Completion Level: 17.20%
2020 SUKUK Payment: N2.5bn
Road/Bridge Works
Kms Covered (2020): 14km
(2) ABUJA-ABAJI ROAD (SECTION 1: INTERNATIONAL
AIRPORT LINK ROAD JCT - SHEDA VILLAGE JCT)

Contractor: Dantata & Sawoe
Contract Sum: N28.6bn
Current Completion Level: 96.11%
2020 SUKUK Payment: N1.0bn
PROJECT COMPLETION
Kms Covered (2020): 2.2km
(3) ABUJA-LOKOJA ROAD: SECTION IV (KOTON KARFE - LOKOJA)

Contractor: Gitto Construction
Contract Sum: N31.08bn
Current Completion Level: 76.0%
2020 SUKUK Payment: N2.5bn
Asphalt Wearing and 1st & 2nd Coat surface dressing on shoulders with lined drains
Kms Covered (2020): 5.5km
(4) DUALIZATION OF OBAJANA JUNCTION TO BENIN
PHASE 2: SECTION 1 (OBAJANA JUNCTION TO OKENE)

Contractor: CGC Nigeria Ltd
Contract Sum: N30.56bn
Current Completion Level: 32.66%
2020 SUKUK Payment: N3.5bn
Ongoing Dualization works
Kms Covered (2020): 63.05km
(5) CONSTRUCTION OF OJU/LOKO-OWETO BRIDGE TO
LINK BENUE & NASARAWA WITH NEW APPROACH ROADS

Contractor: RCC Nigeria Ltd
Contract Sum: N51.61bn
Current Completion Level: 96.7%
2020 SUKUK Payment: N6.0bn
PROJECT COMPLETION
Kms Covered (2020): 5.0km
(6) RECONSTRUCTION OF BIDA-LAPAI-LAMBATA ROAD IN
NIGER STATE

Contractor: CGC Nigeria Ltd
Contract Sum: N33.3bn
Current Completion Level: 13.06%
2020 SUKUK Payment: N5.0bn
CH25+000 - CH35+500, CH43+600 - CH55+000 up to A/C Wearing Course
Kms Covered (2020): 20.9km
(7) RECONSTRUCTION OF MAKURDI-NAKA-ADOKA-ANKPA ROAD IN BENUE STATE

Contractor: Gilmor Engineering
Contract Sum: N27bn
Current Completion Level: 0.53%
2020 SUKUK Payment: N3.0bn
CH70+500 - CH58 (12.5Km), CH70+650 - CH150 (12.5Km) up to A/C Binder Course
Kms Covered (2020): 25.0km
(8) CONSTRUCTION OF ROAD LINKING BARO PORT TO GULU TOWN IN NIGER STATE

Contractor: GR Building Nigeria
Contract Sum: N10.61bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
PROJECT COMMENCEMENT
Kms Covered (2020): 7.75km
NORTH-EAST BREAKDOWN: EIGHT ROADS

(1) KANO-MAIDUGURI ROAD: (SECTION II - SHUARI LINK TO AZARE)

Contractor: Setraco Nigeria Ltd
Contract Sum: N65.31bn
Current Completion Level: 86.62%
2020 SUKUK Payment: N11.0bn
Ongoing Construction
Kms Covered (2020): 53.93km
(2) KANO-MAIDUGURI ROAD: (SECTION III - AZARE LINK TO POTISKUM)

Contractor: Mothercat Ltd
Contract Sum: N45.18bn
Current Completion Level: 91.79%
2020 SUKUK Payment: N2.0bn
PROJECT COMPLETION
Kms Covered (2020): 0km - Toll Plazas/Weighbridges
(3) KANO-MAIDUGURI ROAD: (SECTION IV - POTISKUM LINK TO DAMATURU)

Contractor: CGC Nigeria Ltd
Contract Sum: N51.90bn
Current Completion Level: 80.51%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 94.0km
(4) KANO-MAIDUGURI ROAD: (SECTION V - DAMATURU LINK TO MAIDUGURI)

Contractor: CCECC Nigeria Ltd
Contract Sum: N67.79bn
Current Completion Level: 50.94%
2020 SUKUK Payment: N4.0bn
Main Carriageway Works
Kms Covered (2020): 59.6km
(5) REHABILITATION OF GWOZA-DAMBOA-GONIRI-NGAMDU IN BORNO STATE

Contractor: Hajaig Construction Nigeria Ltd
Contract Sum: N34.60bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.0bn
Site Clearing/Earthworks, Culverts, Pavement & Surfacing
Kms Covered (2020): 15.0km
(6) RECONSTRUCTION OF MAYO BELWA-JADA-GANYE-TOUGO ROAD IN ADAMAWA STATE

Contractor: Triacta Nigeria Ltd
Contract Sum: N22.69bn
Current Completion Level: 14.14%
2020 SUKUK Payment: N3.0bn
Asphalt Wearing & Reconstruction
Kms Covered (2020): 42.0km
(7) CONSTRUCTION OF IBI BRIDGE IN TARABA STATE

Contractor: RCC Nigeria Ltd
Contract Sum: N57.07bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.0bn
Piles and Pile caps for Axis 2 & 3, 4 & 5 Ibi Side
Kms Covered (2020): Bridgeworks
(8) REHABILITATION OF NGURU-GASHUA-BAYAMARI
ROAD: SECTION II (GASHUA-BAYAMARI) IN YOBE STATE

Contractor: Ric Roc Construction Ltd
Contract Sum: N11.77bn
Current Completion Level: 0.14%
2020 SUKUK Payment: N1.5bn
Rehabilitation up to Asphalt Binder
Kms Covered (2020): 13.0km
NORTH-WEST BREAKDOWN: SEVEN ROADS

(1) KANO-MAIDUGURI ROAD: (SECTION I – KANO LINK TO WUDIL WITH LINK TO SHUARI)

Contractor: Dantata & Sawoe
Contract Sum: N55.1bn
Current Completion Level: 67.51%
2020 SUKUK Payment: N4.5bn
Interchange 1,2 & Carriageway
Kms Covered (2020): 58.0km
(2) DUALIZATION OF KANO-KATSINA ROAD: (PHASE 1 - KANO TOWN AT DAWANAU ROUNDABOUT TO
KATSINA STATE BORDER) IN KANO STATE

Contractor: CCECC Nigeria Ltd
Contract Sum: N14.0bn
Current Completion Level: 51.48%
2020 SUKUK Payment: N2.75bn
Ongoing Dualization
Kms Covered (2020): 57.0km
(3) CONSTRUCTION OF KADUNA EASTERN BY-PASS

Contractor: Eksiogulari Nigeria Ltd
Contract Sum: N38.19bn
Current Completion Level: 39.40%
2020 SUKUK Payment: N4.0bn
CH16+000 - CH37+000 (Road Works up to A/C Binder Course), Bridgeworks at Chikaji CH35
Kms Covered (2020): 21.0km
(4) CONSTRUCTION OF KANO WESTERN BY-PASS

Contractor: Dantata & Sawoe
Contract Sum: N22.77bn
Current Completion Level: 66.98%
2020 SUKUK Payment: N4.0bn
Asphalt Wearing; Bridgework (3 & 4); CH 0+425 - CH 9+030 Median Drain & Slope Protection (Bridge 2)
Kms Covered (2020): 12.47km
(5) DUALIZATION OF KANO-KATSINA ROAD: (PHASE II - KANO/KATSINA BORDER LINK TO KATSINA
STEEL ROLLING MILLS ROUNDABOUT)

Contractor: CCECC Nigeria Ltd
Contract Sum: N29.65bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N3.75bn
Ongoing Dualization
Kms Covered (2020): 26.5km
(6) REHABILITATION OF SOKOTO-TAMBUWAL-JEGA-KONTAGORA-MAKERA ROAD: (SECTION I - SOKOTO / KEBBI STATES)

Contractor: Triacta Nigeria Ltd
Contract Sum: N30.45bn
Current Completion Level: 68.52%
2020 SUKUK Payment: N5.0bn
Carriageway Reconstruction
Kms Covered (2020): 40.0km
(7) REHABILITATION OF AJINGI-JAHUN-KAFIN HAUSA
ROAD IN JIGAWA STATE

Contractor: H & M Nigeria Ltd
Contract Sum: N25.03bn
Current Completion Level: 0.00%
2020 SUKUK Payment: N2.5bn
Carriageway Reconstruction
Kms Covered (2020): 12.5km

**SECOND THREAD ON SOUTHERN SUKUK ROADS**
Missing some Tweet in this thread? You can try to force a refresh.

Keep Current with Ajuri Ngelale

Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

Twitter may remove this content at anytime, convert it as a PDF, save and print for later use!

Try unrolling a thread yourself!

how to unroll video

1) Follow Thread Reader App on Twitter so you can easily mention us!

2) Go to a Twitter thread (series of Tweets by the same owner) and mention us with a keyword "unroll" @threadreaderapp unroll

You can practice here first or read more on our help page!

Follow Us on Twitter!

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3.00/month or $30.00/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!