Peter Apps Profile picture
20 Oct, 11 tweets, 2 min read
Lunchtime update from the Grenfell Tower Inquiry:

- Claire Williams reduced to tears as she is shown email from morning of the fire
- Stopped public meetings because of resident complaints in Dec 2013
- Admits 'cursory' review of fire strategy document
On the first point, Ms Williams has been pressed repeatedly over a claim that Rydon provided an assurance that the cladding wouldn't burn. Rydon firmly deny this and there is no documentation of it, despite her claim that it was minuted.
Today, she was shown an email from the morning of the fire where she was asked to provide all the relevant documents for the refurbishment and made no reference at all to this assurance. But as questioning began, she was overcome by tears, necessitating a 30 minute break.
Later, in an extremely awkward passage, she was asked about a claim in her statement that consultation meetings were difficult due to "disruptive conduct from a small number of residents", and as a result TMO consulted on its approach and switched to newsletters and drop ins
Asked to name the residents she was referring to she provided one name and then said tearfully the others are "no longer with us".

I've decided not to repeat that name, as the resident won't have a chance to respond until module 3.
We didn't go into detail about the concerns raised, but it goes without saying that most of the issues residents had have since proved to be entirely valid. The question is why did the TMO not listen and did the restructure of the consulting process serve to quiten dissent?
Ms Williams said more people turned up to drop ins (65% of tower) but accepted news letters were "telling not listening". She referenced other residents who were "good people who knew what we wanted to try and do". Is that really consulting/listening to concerns?
On the fire strategy, Ms Williams saw it shortly after joining the TMO in 2013, but said that amid a lot of new documents, her reading of it was "cursory". She did not pick up that it was incomplete, and said more work needed to be done to review the risk of external fire spread
Millett said that as it was a document relevant to "life safety", "why didn't you read it thoroughly and acquaint yourself precisely with what it said?"

"I was new to the organisation and I had a lot to get to grips with," she replies
Later also saw a spreadsheet where Ms Williams had annotated 'need more fire strategy work' alongside the budget for Exova in November 2015. But none was ever done. Her explanation was that this might have been added earlier and not removed.
Ms Williams continues after lunch.

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with Peter Apps

Peter Apps Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @PeteApps

20 Oct
Grenfell Inquiry currently on hold because Claire Williams broke down in tears when shown an email she sent to TMO colleagues on the morning of the fire summarising some key documents relating to the refurbishment
Pertinence is that she is being pressed very hard over a claim that Rydon gave her assurances that the cladding they were installing was 'inert' and would not burn. She (along with one other TMO witness) say this was said at a meeting and minuted.
But her first witness statement didn't mention it at all and neither, we have just learned, did this email on the morning of the fire. Yesterday, inquiry counsel asked her if the reason was because it was "an attempt to reconstruct a conversation which did not happen".
Read 4 tweets
20 Oct
Despite doing very little to achieve it, minister after minister has said since Grenfell leaseholders should not be made to pay for cladding costs.

Yesterday, Stephen Greenhalgh finally abandoned that position: insidehousing.co.uk/home/home/buil…
Worth taking a moment to reflect that "it's the law" isn't a very good excuse for a minister in a party with an 80 seat majority, who was in fact being asked about plans for new legislation.

It's you guys that make the law, Stephen.
Also, judging by my Twitter and Whatsapp over the last 12 hours, this statement has marked a turning point in the way affected leaseholders view government.

The small remaining 'if only we can get them to listen' optimism has been replaced fairly unmitigated anger.
Read 4 tweets
19 Oct
Lunchtime update from the Grenfell Tower Inquiry:

- TMO project manager destroyed notes and diaries about project a year after fire
- Unable to explain why she didn't query incomplete fire strategy in 2016
- Grilled about risk assessment raising concerns about cladding in Nov 14
The bombshell news from this morning at the inquiry was that Claire Williams "binned" her notes and records when she left the TMO in 2018, despite knowing the public inquiry was underway. We've covered in a story here: insidehousing.co.uk/news/kctmo-pro…
This revelation came from the further news that her colleague, Peter Maddison, had been keeping his diaries and record books at his home and only disclosed them to the inquiry on Friday night. There will be a delay this week so they can be read by all parties.
Read 10 tweets
19 Oct
BREAKING: A 1,000-home estate of mostly student housing in west London is to be evacuated immediately due to a "multitude" of fire safety issues which mean resident safety can no longer be guaranteed insidehousing.co.uk/news/housing-a…
Paragon Estate (six towers, largest 17 storeys) have had known fire safety issues since December 2017 relating to cladding and fire breaks. But new intrusive inspections have now resulted in advice from consultants that they are not safe to occupy
These towers were built by Berkeley Group in 2006 using offsite (modular) construction and the largest tower was feted as the tallest modular building in the country on construction. They are currently owned and managed by Notting Hill Genesis.
Read 7 tweets
19 Oct
Pretty astonishing start to the inquiry this morning, as it emerges Peter Maddison of the TMO has just disclosed his diaries and workbooks covering the refurbishment, having previously kept them at his house and not mentioned them to the inquiry or police
They run to more than 300 pages in length and cover the period January 2013 to May 2017. Mr Maddison will be asked why he didn't mention them until he disclosed them through his solicitor on Friday at 16.40. Will necessitate a break this week for other parties to read
😱😱😱

When Claire Williams from the TMO is asked about this, she reveals she "binned" her own note books relating to the refurbishment in May 2018 when she left the TMO. This is AFTER the fire and launch of inquiry + police investigation.
Read 5 tweets
17 Oct
Just 189 of 458 buildings in the ACM programme have completed remediation in 3 years. The target for full completion was June 2020.

Instead of trying spin this as a success, ministers should be learning from what went wrong - especially as the next programme has c2500 buildings
What the government proved with its efforts to get building owners to pay is that it can only succeed with the lowest hanging fruit, and even then usually only if a warranty provider or developer steps in. It also takes an unacceptably long time.
They have now made this job harder, by proving that they will provide funds rather than take punitive measures if the owner refuses to act, and that they are content for leaseholders to pay if push comes to shove. Where is the incentive for an owner to pay?
Read 5 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!

Follow Us on Twitter!