The drive unit is completly closed. Inside works begun a few weeks ago. This building acts as a template.
Paint roof is ready, BIW, GA, ST almost done. Roofing CA begins.
Machines get loaded into the painting since end of Ocotober.
2/12
2. Waiting for next permission
The permission will include among other things tree clearing and machine integration. The reason for waiting is that the descission needs to be legally incontestable. Therefore a verbatim record needs to be analysed.
3/12
Its the protocoll decided at the public discussion at the 22nd of September in #Erkner. For the objectors this was a big thing. Maybe a small but loud part of the objectors hoped it would bring a delay. Actually a result log is more common.
4/12
3. Compensation of lost time
The permission was awaited at the first of October according to some sources. Means there is a time delay Tesla already adapted to. They will try to ramp up the processes and already applyed for the permission to expand the working hours.
5/12
4. The team spirit
Time and the will to do something big and unforgettable is what drives all involved ppl. Someone from the Tesla team said: "We do not calculate in weeks, not in days: with us everything is timed by hour." and Tesla does not think about to much about ...
6/12
... mistakes, they present innovative solutions in a short time.
Participating construction companies speak of a lighthouse project and workers I talked to said they are proud to be part of this big project and want to see it succsess.
7/12
5. The next steps
All are waiting for further permissions. Besides that more and more worker and machines arrive a the site.
In addition an importand step is the new B-Plan (Development plan) the community representatives have to decide in the next days. Dec. 15th I think.
8/12
This has to be positive decided BEFORE the final #GigaBerlin permission can be made.
The developement plan includes among other things importand steps to connect #GigaBerlin to the existing infrastructure.
We will see that PA, CA, GA, ST, BIW grow together to one big building. The roofs will be closed in the next 2 weeks as well a the walls. Further windows will be installed as well as venting and heating machines and the #GigaPress machines might arrive before Christmas.
10/12
What do you think about a monthly status quo briefing with rotating responsibility @tobilindh, @Gf4Tesla? We should implement a structure for better later comparision and should think about to set up a document. Reading in threads might be difficult 🤔
11/12
Annotation
BIW: Body in white
ST: Stamping
CA: Casting
GA: General assambly
DU: Drive unit
PA: Painting