There has been a steady decrease in the losses in the electricity Distribution Network (AT&C Losses) in the country over the past 15 years, wherein these losses have reduced from 25.72% in the year 2014-15 to 21.83% in the year 2019-20. Image
Due to various reforms taken up by GoI and the state governments, more states have moved from higher distribution loss (AT&C loss) levels to lower AT&C loss levels over the last 10 years. Image
The following distribution utilities have registered AT&C loss of less than 15% in FY 2019-20. Image
Revamped Distribution Sector Scheme is a Reform based and Results linked scheme recently approved by the Govt. of India.
The scheme shall provide result-linked financial assistance to DISCOMs for strengthening of supply infrastructure based on meeting pre-qualifying criteria and achieving basic minimum benchmarks.
The Revamped Distribution Scheme targets AT&C losses at 12-15% by FY 25-26 as against current levels of 21-22%.

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with Ministry of Power

Ministry of Power Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @MinOfPower

28 May
A meeting was called by Secretary , Power , GoI to proactively finalize the Guidelines on developing cyclone resilient distribution and transmission infrastructure .
Apart from officials of Ministry of Power , officials of the CEA and those of cyclone affected States as well as the officials of CPSUs working under the Ministry were present in the meeting .
Under the Guidelines , the DISCOMs are to set up cyclone resilient infrastructure in the coastal belt Upto 20 kM from the coastline and thereafter , progressively upto 60 kM.
Read 10 tweets
27 May
Ministry of Power has constituted a Task Force on Cyclone Resilient Robust Electricity Transmission & Distribution infrastructure in coastal areas of the country to examine types & nature of damages to electricity infrastructure and to recommend preventive & mitigation measures.
Measures include various emergency preparedness plan, Design & Technological aspect, steps to be taken by utilities for capacity building to create cyclone resilient infrastructure to shorten restoration time (including ERS) and limit the impact of disaster.
Preparedness plan is to:
•Meet any contingency
•Reduce response time for assistance.
•Identify major resources, man power, materials etc. for making the plan operational
•Optimum use of available resources
•Improve the plan periodically based on learning over the time
Read 4 tweets
4 Apr 20
Hon’ble Prime Minister has appealed to the people to voluntarily switch off their lights between 9:00 pm to 9:09 pm on the 5th of April. #IndiaFightsCorona
Some apprehensions have been expressed that this may cause instability in the grid and fluctuation in voltage which may harm the electrical appliances. These apprehensions are misplaced. #PoweringIndia
The Indian electricity grid is robust, stable and adequate arrangements and protocols are in place to handle the variation in demand. #PoweringIndia #IndiaFightsCorona
Read 6 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!

Follow Us on Twitter!

:(