15day stock is idle but even week stock is normal, old records shows that.
Just hve a look at PowerPlants of #Chhattisgarh except Bhilai all r within 5 to 60km from Mine where coal can reach in 2hrs
Moreover Lara n Madwa have CaptiveMines not dependent on CIL
LARA NTPC plant has a captive mine #Talaipalli if it is having 6 day stock... whom shall they blame ??
Madwa CHPGCL has Gare3 captive mine with #Adani as MDO ... they too have 6 days stock... whom should they blame ??
Now Delhi Power Minister says coal supply is not regular..
Delhi power plants have coal linkage with NCL Singrauli where normal production is reported in previous months. So how come Coal is not reaching Delhi??
Will Ministry of Coal n Power share all production n supply data??
CIL's production in the April-September 2021 period increased 5.8 per cent to 249.8 MT, compared with 236 MT in the year-ago period, the BSE filing said.
Another PSU SCCL reported 30 MT prod. against 18 MT last year
Strange to note that Government is claiming huge coal shortage
Even Captive coal miners have reported higher coal production in 2021
Then why Coal is not reaching to power plants and that too Delhi ??
If Delhi phases a Blackout... then over whelminhly an opinion would be made to allow more coal projects...