Kerala Silverline

Not a war of words: Let truth vanquish falsehood

This article today in Hindu says MD/KRDCL wrote to SYSTRA rejecting Alok Verma's report & asked "Systra to re-work the alignment and cost and submit a fresh report."

Good article..1/3

thehindu.com/news/national/…
..but would urge editors of Hindu to fully expose this campaign of disinformation. Please ask MD/KRDCL to substantiate his claim that this is Alok Verma's report.

The truth: It is Systra's report (See scan of the cover of the report).

Did Systra submit a fresh report? .. 2/3 Image
..If so, where is that report.

The truth: SYSTRA did not submit revised report. Thus, this report of 18.3.19 stands as the final Preliminary Feasibility Report.

I have clarified this in my recent press note of 25.4.22. Copy below... 3/3

#Campaign_of_Disinformation_by_KRDCL ImageImageImage

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with Trains Are Best, Alok Kumar Verma, IRSE (Retd)

Trains Are Best, Alok Kumar Verma, IRSE (Retd) Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @trains_are_best

Apr 29
Kerala Silverline: My take on Panel Discussion

People of Kerala get a bigger dose of disinformation as Suboth Jain bats for KRDCL.

There is the added dose of seize mentality: Rly Bd/Central Govt is not interested in raising speed on the existing lines & building new lines..
..for higher speed of trains, so go for loan from Jica even if it means building a standalone line on SG which will be subsidized for ever by the taxpayer for travel by the affluent.

So govt subsidy for the affluent by the taxpayer.

I will post a detailed analysis tomorrow.
..To R. V. G. Menon:

Sir, you came out swinging! Suboth Jain couldn't give straight answer to even question. For example, your question about existing trains not being able to run on the Standard Gauge Silverline.

#K_Rail #Kerala_Silverline
#AlignmentSurveys #GroundSurveys
Read 4 tweets
Dec 1, 2021
I am an alumnus of IIT Kharagpur & IIT Delhi.

In 2006-08, I developed a solution to the problems that Indian Rly was facing in building the rail link to Kashmir.

My idea was examined and was being considered for implementation, but soon a vicious campaign to scuttle the..1/6
..process began.

I had to seek Court intervention. The Courts ruled that Railway Board acted against me for the malafide purpose of scuttling the review.

An Expert Committee appointed on orders of Delhi HC said that ongoing construction should be scrapped and my alignment..2/6
... should be adopted to start construction afresh. But, Rly Board refused to accept the unanimous recommendations of the committee.

Today, not just the Kashmir Rail Link Project but all 7 projects in Himalayas are in a deep mess because of the flawed alignment methodology..3/6
Read 16 tweets
Nov 26, 2021
K-Rail and Railway Board's history of approving projects without proper ground surveys & feasibility studies

With Railway Board still dragging its feet about rescinding the In-principle Approval for the K-Rail plan, it is necessary to ask why Railway Board refuses to learn..
.. lessons from its fiasco in Himalayas where since 1997, Rly Bd approved alignments for as many as eight new line projects in the challenging landslide-prone terrain without any ground surveys, on just paper alignments.

My post in the link above contains a detailed account.... ImageImageImageImage
..The latest victims of this approach are the plan for the semi-highspeed line in Kerala & the strategically important Bilaspur-Manali-Leh line.

#KeralaSemiHighspeedProject #Kashmir_rail_link #Chenab_Rail_Bridge #Ruling_Gradient #AlignmentSurveys #GeologicalSurvey #railwayboard ImageImageImage
Read 4 tweets
Nov 25, 2021
K-RAIL: WHY HAS RAILWAY BOARD NOT TAKEN ANY ACTION AGAINST MD/KRDCL FOR SUBMITTING FEASIBILITY REPORT BASED ON GOOGLE EARTH AND NO SURVEYS OF GROUND CONDITIONS & RIDERDHIP & DECIDING TO ADOPT STANDARD GAUGE?

Will Rly Board go on giving in-principle..1/3

english.mathrubhumi.com/news/kerala/e-…
..approvals in future also to projects involving this magnitude of public expenditure based on such fraudulent, concocted & cooked up feasibility reports?
.. 2/3

#Kerala_Silverline_Project
#KeralaSemiHighspeedProject
#AlignmentSurveys #IR_EngineeringCode
Read 7 tweets
Jun 6, 2020
My plan for upgradation and expansion of the Indian Railway network:

1. Build about 15,000 km of 200-250 kmph lines to cover the GQ and it's diagonals & link other major cities. About half of this will be by upgrading the existing lines and half as new lines. Total estimated..
...cost: About INR 5.0 lakh crore over a period of 7 to 10 yrs.

2. No more DFCs. Complete the ongoing Eastern and Western DFCs and use them (with some modifications) for carrying freight & slow passenger trains.

3. Drop all ongoing surveys and feasibility studies to build..
... Bullet Train lines. India does not need and will not be able to afford Bullet Train lines for at least next 15 yrs, by when improved technologies like Maglev are likely to be available for speed more than 250 kmph.

This plan also entails:

1. Massive upgradation of the...
Read 14 tweets
Feb 28, 2020
In the coming days, resolve of the Government of India and Railway Board to upgrade India's rly system to high speed (160-250 kmph) will be tested. Powerful foreign lobbies, which represent the interests of the manufacturers of airplanes and automobiles and the oil companies,....
... have been trying to cripple the railways in India by preventing it from raising speed and line capacity. Their first success came in 2004-06, when the Govt decided to build the Eastern and Western Dedicated Freight Corridors instead of a 200-250 kmph line which would have...
.... benifited both the passenger and freight transport (both DFCs and 200-250 kmph lines cost the same). Their next success came in 2017, when the Government decided to build the Ahmedabad-Mumbai Bullet Train line instead of the much cheaper and better option of 200-250 kmph..
Read 18 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Don't want to be a Premium member but still want to support us?

Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal

Or Donate anonymously using crypto!

Ethereum

0xfe58350B80634f60Fa6Dc149a72b4DFbc17D341E copy

Bitcoin

3ATGMxNzCUFzxpMCHL5sWSt4DVtS8UqXpi copy

Thank you for your support!

Follow Us on Twitter!

:(