TCNNIGERIA Profile picture
May 5 17 tweets 5 min read Twitter logo Read on Twitter
TCN LAGOS REGION TAKES DELIVERY OF A BRAND NEW 300MVA POWER TRANSFORMER . . . Boosts Transmission Capacity

The Transmission Company of Nigeria (TCN) took delivery of a brand new 300MVA 330/132/33kV power transformer at its Lekki 330/132/33kV Transmission Substation on Electricity Electricity ImageImage
April 30, 2023, the latest addition of new transformers delivered to the substation. Earlier, the substation received two brand new 60/75MVA power transformers in February and three heavy-duty truckloads of transformer components in January, 2023, among others. Electricity Electricity Electricity Electricity
TCN Management through its Lagos Region has continued to ensure prompt execution of transmission projects within the Region. This entails the upgrade or total overhaul of its equipment where needed to achieve a more effective and efficient bulk transmission of electricity to the
distribution load centers of the Ikeja and Eko DisCos and reduce to minimal, downtime that would have resulted from equipment failure. The Region equally undertakes the prompt maintenance of equipment to further preserve its lifespan.
On installation, the 300MVA 330/132/33kV
power transformer will add 240MW to the Lekki Substation capacity. Presently, arrangements are being made to put the transformer on the plinth to enable its installation.
Meanwhile, under Lagos Region, several substations and line projects have been completed in the last one
year, some of these include:
- Reconductoring and commissioning of the New Ikorodu/Shagamu 132kV line
- Installation of 1x60MVA transformer at Egbin 132kV Substation
- Installation of new 60MVA 132/33kV transformer at Itire 132kV Substation
- Diversion of Aja/Egbin 330kV
lines 3 & 4 to Aja/Omotosho/Epe 330kV lines 1&2
- Replacement of 3nos defective circuit breaker interrupter of T1 45MVA transformer secondary circuit breaker.

The Region has equally changed several other circuit breakers in different areas of the transmission region.
The Lagos Region is also undertaking several transmission projects, which are at various stages of completion. Some of them are as follows:
- Construction of 2x60MVA 132/33kV Eko Atlantic Transmission Substation
- Installation 300MVA 330/132kV, 2X100/125MVA transformers at
Alagbon Substation
- Installation of 300MVA 330/132kV, 2x60/75MVA 132/33kV transformers at Lekki Substation
- Installation of GIS indoor equipment at Akoka Substation
- Installation of 60/75MVA 132/33kV transformer at Akoka Substation
- Installation of GIS indoor equipment
at Amuwo Substation
- Installation of 60/75MVA 132/33kV transformer at Amuwo Substation
- Upgrading Ijora Substation with 100/125MVA power transformer
- Installation of additional 100/125MVA at Ijora Substation
- Installation of GIS indoor equipment
at Itire 132/33kV Substation
- Reinforcement with 60/75MVA 132/33kV transformer at Itire Substation
- Upgrading with 2x100/125MVA power transformers at Maryland Substation
- Upgrading with 2x100/125MVA transformers at Ota Substation
- Upgrading of Alausa Substation with 1X100/125MVA power transformer
- Conversion of transformer T1-45MVA sec & 3Nos. 33kV feeders indoors to outdoors at Alausa 132/33kV Substation
- SCADA system – installation of
grid metering pane for the 132kV & 33kV Circuits at Alausa Substation
- Rehabilitation of the 132/33kV control room at Alausa Substation
- Upgrading of Akoka Substation with 2X60MVA transformer
- Installation of 100MVA power transformer at Ajah Substation
- Installation of 30MVA and 60MVA power transformers at Oworonshoki Substation
- Construction of additional 3x33kV feeder bay at Oworonshoki Substation
- Installation of 100MVA power transformer at Isolo Substation
- Upgrading of Isolo Substation with to 60MVA power
with 60MVA power transformer
- Upgrading of Itire Substation with 60MVA power transformer
- Construction of 3Nos. 33kV bays at Ojo Substation
- Upgrading of 2x45MVA with 2x100MVA power transformers at Agbara Substation
- Construction of additional of 3X33kV feeder bays at
Agbara Substation
- Installation of additional 1X100MVA, 132/33kV transformer at Oke-Aro Substation

TCN Lagos Region also installed several feeder bays in different substations such as Oworonshoki, Oke-Aro, and Egbin, among others. In addition to these, other projects have
have been proposed to further enhance power transmission within the Region.

Ndidi Mbah
GM, (Public Affairs)
5/5/23
#tcnnigeria
#TCNCares
#electricity
#power
#projects

• • •

Missing some Tweet in this thread? You can try to force a refresh
 

Keep Current with TCNNIGERIA

TCNNIGERIA Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

PDF

Twitter may remove this content at anytime! Save it as PDF for later use!

Try unrolling a thread yourself!

how to unroll video
  1. Follow @ThreadReaderApp to mention us!

  2. From a Twitter thread mention us with a keyword "unroll"
@threadreaderapp unroll

Practice here first or read more on our help page!

More from @TCN_NIGERIA

Jan 7
TCN'S WHEELING CAPACITY AND TRANSMITTING PEAK GENERATION

TCN's wheeling capacity as simulated by its System Planning Department is 8,100MW and since the simulation was carried out, TCN has continued to expand the nation's grid by rehabilitating and upgrading brown field/existing TCN's Wheeling Capacity  Transmission Capacity  MD's Quotes TCN's Wheeling Capacity  Transmission Capacity  MD's Quotes TCN's Wheeling Capacity  Transmission Capacity  MD's Quotes TCN's Wheeling Capacity  Transmission Capacity  MD's Quotes
projects and building new/green field projects.

The projects are in various TCN's old or new Substations nationwide, from the North to the South, to the East and West. The projects - substations, lines and systems operations projects are numerous and on ground nationwide.

/2
Several are already in circuit while others are ongoing.

TCN's capacity & capability to transport bulk power is presently above the current bulk power generated into the grid and quantum power being taken by the DisCos.
TCN's capability to efficiently transmit the quantum of
/3
Read 11 tweets
Jan 6
TCN COMPLETES CONSTRUCTION OF BRAND NEW TOWER AT KATAMPE
…Restores Bulk Supply Through its Central Area Gas Insulated Substation on Thursday, 5th January, 2023 at about 09:48 pm. The tower construction work and stringing of the Katampe-Central Area lines 1&2 were carried out Construction of brand new transmission tower  Katampe New TrConstruction of brand new transmission tower  Katampe New Tr
by TCN’s contractors in conjunction with TCN Engineering and Lines Crew.

Presently, the Katampe-Central Area Double Circuit transmission lines are supplying bulk electricity to TCN’s 3x60MVA Central Area Substation and the Abuja Electricity Distribution Company (AEDC) has
equally started off-taking power from the substation to its customers in Abuja Metropolis.

Recall that on the 7th of December, 2022, TCN’s tower No. 20 at Katampe, was brought down by a truck carrying chippings, causing restricted outage in some areas within the Abuja
Read 5 tweets

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3/month or $30/year) and get exclusive features!

Become Premium

Don't want to be a Premium member but still want to support us?

Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal

Or Donate anonymously using crypto!

Ethereum

0xfe58350B80634f60Fa6Dc149a72b4DFbc17D341E copy

Bitcoin

3ATGMxNzCUFzxpMCHL5sWSt4DVtS8UqXpi copy

Thank you for your support!

Follow Us on Twitter!

:(