CCECC Nig. Ltd., upon work #resumption in May from the lockdown, made efforts to regain all lost time in order to complete all lanes at the section covering Trade-Fair to LASU on the Lagos–Badagry Expressway project at a constrained time frame.@FMWHNIG@LSPWC_Official@LASGWorks
Over 2.7km of construction has been completed on the service lane and 2.3km on the toll lane–Badagry bound. The installation of drains, kerbs, barriers, etc. is ongoing. The proposed diversion at Iyana-Iba is at the stone dust filling, spreading, and compaction stage.