🚧🛠️ Quick Pour Concrete Cycle Lane Kerbs 🛠️🚧

This is a nerdy thread about *concrete kerbs* but I promise it will be fascinating.

This new construction technique could quickly see concrete kerbs added to protect cycle lanes overnight. No more plastic bollards.
Traditionally adding concrete kerbs to cycle lanes similar to Benildus Avenue would take 2-3 years.

Engineers would need to redesign the road's drainage, go to tender and spend 6 months at construction.

Construction here will be completed in less than 2 weeks.
It took weeks to plan this trial, but future cycle lanes could see the whole process done in weeks.

Changing the rate of delivery from 2-3 years to 2-3 weeks will mean we can rapidly build out a safe cycling network in Dublin. That's a lot more happy cycling.
This is a trial by the National Cycle Design Office that was recently established by the National Transport Authority. @dlrcc are the local partners.

If this trial and one on nearby Goatstown Road are successful, there are plans to roll this technique out across the country.
Here's some photos of the two major machines involved in the construction. The first machine digs a trench in the existing road. The second machine pours the concrete curbs into that trench.
A key part of why this can be built so quickly is that the engineers don't need to make any changes to the road's drainage. The gaps in the concrete kerbs allow rain water to flow to the existing drains at the side of the road. The gaps will be protected by a single bollard.
This approach cannot be used in all circumstances. Benildus Ave is a wide road with painted cycle lanes. This project doesn't move any of the existing kerbs on the road. That's normally the complex part as it requires drainage changes, which requires you to dig up the whole road.
For the concrete kerb nerds out there here you go:

(I know you all exist. Don't lie to yourself. You're zooming in on these photos right now)

Photo Credits: J Shanahan
The kerb is 10cm on the motor traffic side. It's an imposing kerb that most vehicles would not easily be able to mount. On the cycle lane side it is slightly angled so it doesn't catch a person's pedals.
I'm honestly so excited about this project. It has huge implications for how quickly councils across the country could start delivering high quality safe and comfortable cycling infrastructure.

Me right now:
There's more information on Benildus Avenue here: trello.com/c/jABHmaEe/128…

and the nearby project on Goatstown Road that will start construction soon: trello.com/c/jNCB3z7u/129…
So what do you think?

Are you excited? Do you have questions? Are you wondering if this approach will work on your normal cycling route?
Missing some Tweet in this thread? You can try to force a refresh.

Keep Current with Kevin Baker

Profile picture

Stay in touch and get notified when new unrolls are available from this author!

Read all threads

This Thread may be Removed Anytime!

Twitter may remove this content at anytime, convert it as a PDF, save and print for later use!

Try unrolling a thread yourself!

how to unroll video

1) Follow Thread Reader App on Twitter so you can easily mention us!

2) Go to a Twitter thread (series of Tweets by the same owner) and mention us with a keyword "unroll" @threadreaderapp unroll

You can practice here first or read more on our help page!

Follow Us on Twitter!

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just two indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member ($3.00/month or $30.00/year) and get exclusive features!

Become Premium

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!