We regulated Idukki since July 20 to keep it at check looking at various global forecasts for 14 days, not blindly following IMD.
The professional reservoir management of KSEBL resulted to save Kochi from flooding last week, as Idukki absorbed all very heavy flows
Idukki seen 600 to 800 cumecs inflow during last couple of days. All that were absorbed by Idukki, when Aluva Siva temple submerged. Dread to imagine NO Idukki-Idamalayar then, Kochi airport & many low lying areas would be under water.
Reasons for coal shortage is mainly due to 3 reasons.
1. Huge Arrear outstanding against GENCOs 2. Single Window e-auction for non-linked domestic coal 3. Huge price of coal at international market due to Ukraine war
As per official PRAAPTI portal, the undisputed dues outstanding against GENCOS from the DISCOMS as of April 2022 had touched 1.068 lakh crores.
Many DISCOMS arrear is outstanding from 6 months to more than 12 months.
So cash flow to GENCOS throttled
So the GENCOS together owe around Rs.8000 crores to the Coal India Ltd.
Systematic constrains, unstainable subsidies, huge distribution losses & failure of regulatory regime to see DISCOMS run in a sustainable manner is affecting India's energy security.