@MarcMillerVM@BowhunterJonny@sunlorrie As I see the constant chatter about progress with FN infrastructure, I can no longer sit back and let this continue without a concise, and detailed explanation of what we see in regard to both FN Infrastructure, and other infrastructure/1
We have a serious problem with the construction of water treatment plants, sewage treatment and the distribution of both.
For the life of me, I cannot wrap my head around why we cannot fix this. The Lib government says they have a plan..... /2
There is no way that anyone in Ottawa has a workable plan - and that is because they either do not understand the scope of the problem, or that they are "delaying, and distracting" in regard to a solution 3/
I have done so many threads on how the projects are procured via ISC (INAC) but I can see that even that is not enough to accurately reflect what happens on the ground once a project starts. People ask me why projects fail - here it is folks, a big part of it. 4/
Once Treasury allocates those funds via a contribution agreement with the FN, a design engineer is obtained and a process begins in which the high level estimates are done, and the project is actually engineered. This is also an invited low-bid situation believe it or not. 5/
Why do projects fail, go off the rails, see delays, cost overruns? The first reason is engineering, and I am going to focus on that first - because it is critical to understanding the false glee on progress in FN infrastructure spouted by Gov. 6/
You need a few key things in a project - geotechnical investigation for ground conditions, water chemistry analysis, knowledge of currents for discharge in the case of sewer and water, and a competent understanding of process mechanical, and electrical systems. 7/
All of this engineering investigation needs to be done prior to the acceptance of a design, and most definitely prior to tender for a general contractor (GC). But I have multiple projects on hand dating from 2009 to today to show it doesn't always happen. 8/
As with EVERY single project involving fluids (sewer, water, oil and gas), you need something so basic and it is not being provided to the contractor at time of tender in every case. It is called a P&I - process and instrumentation. 9/
This P&I literally tells the contractor how the guts of the system will work. It explains piping, direction, valves, instrumentation, and - this is key - how these systems TALK TO ONE ANOTHER!!!! What if I told you that some engineers DO NOT PROVIDE AT TENDER!! 10/
The other key - what we call a control narrative. This is the engineer's statement on how he would like to see mechanical systems and electrical systems to work together for complete system integration. What the fuck does a GC do when he doesn't know what it is? 11/
I will add in here an example: Marten Falls water treatment plant. I was there, as a sub. And, there was not a complete and accurate set of drawings issued to the subs that detailed all of the above. SO SIMPLE - accurate drawings. 12/
In Marten Falls, there was improper sizing of motors to the available voltage of electricity. Come on folks - this is basic stuff. No indication of all piping needed for flow, no accurate P&I, no verification during shop drawings that voltage matched mechanical motors 13/
In Marten Falls, which just declared a state of emergency on a new upgrade completed in 2019, the operator had to run the plant in manual because the SCADA from the old side, didn't communicate effectively with the new side.... 14/
Now, lets move to Manitoba. In 2016, another FN took a hit on a project that was never started off correctly. In this case, accurate geotechnical was never done. Borrow locations (for clay) were botched in design phase, ground water missed 15/
The result was a massive claim, and change order. And, it directly involved the spilling of sewage into groundwater between the school and only well site for the community water treatment plant. How far apart? Less than 100 ft each side. Well casing was also cracked 16/
Detailed water tests showed that our excavation in high ground water conditions was impacting the turbidity results on the water treatment plant. And, when I put this all in writing - the reply? It is ok, nothing to see here. 17/
Attached below - a redacted list of concerns the First Nation presented to ISC, the design engineer and the GC. They nailed it - they asked the hard questions and they got the shaft. Not the engineers and project manager on the project. How does this help a FN? 18/
In 2016 - I personally shared information regarding this project with the PMOs office, Carolyn Bennett, Environment Canada, Health Canada, MB Conservation, MB office of drinking water... the response? Nothing. BTW - I kept those comms. 19/
Another First Nation - Tataskweyak Cree Nation - similar stories. I will start with the old lagoon because it relates directly back to good engineering. In 2017, during massive flooding, the lagoon had to be spilled. This prompted the FN to ask me to assess the pumps 20/
The FN complained they kept burning out, and as a result, ISC was just building new ones 2 miles away, uphill, with not enough clay...
So, I did. It turns out, we had exposed bus bars in the outdoor panel, non weather proof, and the phases were unbalanced. 21/
Now, I am no rocket scientist by any means - I'm really just another dumb contractor playing in the mud - but even I know that unbalanced power coming into a panel tends to burn out motors pretty fast.... 22/
Same community - water treatment plant - in 2000 approx - an upgrade was done. It was supposed to take a pretty solid treatment process, and add capacity for an expanding community. But that is not what happened. Instead, the old side never got hooked up. 23/
The new side never had the above ground reservoir epoxy coated, and sealed. It has been bleeding ever since as the raw water chemically reacts with the unsealed concrete. See attached. 24/
@MarcMillerVM@BowhunterJonny@sunlorrie For this particular FN, the old treatment process was ripped out, the old side which gave redundancy in case of one side failing, has been offline for TWO DECADES!!!! The new side has no VFD's to manage backwash flow. 25/
In addition - because of only adding chlorination, and no UV - the THMs have consistently exceeded safe levels from 2014 to today. Why no concern? Oh, I remember - in that particular meeting in July 2017 - we were told "the Gov takes time"...... 26/
In the above - the older carbon filtration system, and pre-treatment actually did a pretty good job at reducing THMs produced from raw source waters excessively high in methane. Why so high? Well, its in a Hydro catchment area of course.... like Kaschewan.... 27/
If ISC, the Federal Gov, and the various Provincial Governments cannot manage the actual construction process on the ground - how on earth can you tell CDNs that there is a plan. If you can't figure out how to manage a single project effectively... there is no plan. 28/
I am so tired of every single politician in Canada waving the Indigenous issues matter flag when they really don't have a clue to fix it. As Canadian taxpayers (and we all pay taxes in some form) - why aren't we forcing accountability? 29/
Hands down - we have solutions - and it is called getting competent people back into this process, forcing accountable engineering, project management and delivery. CDNs need to wake the hell up if they want this fixed. 30/End (for now)
8.1/ As an aside, most contractors prior to 2010 were providing Issued for Tender, and separate Issued for Construction drawings prior to shovels in the ground. The second dwgs provided accurate changes made via addendums to scope. Now, we often get only bid drawings.
In Manitoba, Manitoba Hydro actually had to make it a requirement that our lazy engineers start providing accurate electrical drawings, with P&I, motor sizing etc. WTF? That was 2017. No joke.
@MarcMillerVM As an aside, in TCN, I had to fight with the design engineer for 18 months to get a detailed control narrative for the lagoon blower building. We got to commissioning, and all of the questions I asked from 2011 to 2019 were ignored. I had to source it.
How many people know about the boondoggle in TCN for the lagoon project started in 2010-2011 through 2019 and the final budget? .....
OK - not done. On another FN project, take a look at what I had to send to the engineering firm, ISC, and GC: they couldn't figure out how to finish the project efficiently on a 9 year project blown right out the door. This was project was such a shit show. See attached 31/
32/ On Feb 3, 2016 I sent a 4 page letter to the PMO's office, essentially as a whistle-blower. At the same time, I sent a more detailed one to Carolyn Bennett. I was so naive, and was completely blown off. It is my intention to post those letters here, un-redacted if possible.
Attached - this is page 1 of the first letter sent. I never received a single response. I thought, like many others, that the concerns of women, Indigenous people, and the environment were of the utmost importance. I was wrong. 33/
On Page 2, I begin to really lay out some serious concerns. Some names are redacted, but you get the picture.
On Page 3, I really went into some serious issues. I detailed every step we took to help the First Nation.
And on the final page - I detail why this is so important. But my concerns were BLOWN OFF!
This was when I knew that politicians don't give two shits about Indigenous people, women in general.
@PierrePoilievre@AlexpiersonAMP Now, I am going to talk about how poor, and lazy engineering is running our infrastructure projects into the ground. We have put eng firms on a pedestal, when in fact, poor engineering is destroying the industry, and costing taxpayer $$$$
Just sent to me - an email thread once again detailing how P. Eng's do not understand the process they are supposed oversee on behalf of clients, and have become lazy in how they carry out their jobs. We are going to discuss Issued for Construction drawings - and its importance.
For some reason, eng firms have put profit over client liability and the public safety. And, this translates into the world of infrastructure, and a project being derailed in a big way. Prior to about 7 years ago - every major contract had 2 parts - Tender drawings, and IFC dwg
@222Minutes Ok, here goes: on FN's, there is what we call a FNIB done every year. This is the infrastructure budget required. A budget (based on Indian Act formula) also is prepared for healthcare, housing, childcare. Sewer, water, housing builds all under infrastructure. Schools separate.
@222Minutes The budgets run yearly - April 1 to March 31, with budgets paid out normally in quarterly installment. There is a set formula, set $$ for everything and you can't move $ from housing to maintenance if you run short. Or vice versa. But the formula allows almost nothing on ops.
@222Minutes All infrastructure like water treatment plants, roads on reserves, schools come from federal $$. Environment covered by Environmental Canada, not provincial legislation. Healthcare by Health Canada, not provincial. Services used are billed back to the feds. No health cards!!!
Construction in any form is nuts. I happen to do both residential and commercial work and the problems I encounter are so out of this world. Today we had two totally different issues arise - and they are eye openers:
Residential issue: we are doing a federal reno for Health Canada on a FN. Client house is lived in by older couple and 6 kids/gk's. GP is likely experiencing early onset of dementia and outbursts are starting to get violent. It's grumpy old man syndrome on steroids.
We are busy working around GP because he won't move into the temp housing, and making it bearable. We did roof, windows, doors, ceilings drywalled, painted, flooring, painting, and new bathroom. It's a messy job. Living there will be tough. But he is.
As I read various threads today - I see that many have no idea what misogyny really is. Today, it seems easier to focus on pronouns rather than real issues - and this path will only lead to reversal of hard won battles by true advocates of women's rights. That path is misogyny.
Initial fights were for the right to vote, the ability to take part in the political process, equal protections under the justice system, and the ability to have equal access to a variety of opportunities. This includes the establishment of a category for female sport.
Somewhere along the way - that fight for equality has been hijacked by people that haven't a clue what it feels like to caught up in a truly unequal situation. At 28, I had no barriers to my entry to the military here in Canada, but I had to compete based on merit to get in.
So - I have interesting situation - I have to basically live my life without antibiotics. Been this way for about twenty years. Since I was young, I have had a life threatening allergy to penicillins, and all cephlasporins. My toolbox got very small due to antibiotic resistance.
As time went on, anti-inflammatory meds were added to the list along with different types of freezing. A trip to the dentist for a filling left me with temp paralysis on one side of my face, and a trip to the emergency room for an Epi.
That is when we found out that some allergic reactions will not respond to an Epi. That brings you into medications made with blood products.
I see a lot of comments decrying the CPC's apparent "association" with various pro-life groups, and how that association is used to undercut support of conservatives overall. This is a fundamental mistake, and one that continues to erode Charter Rights.
When you take actions to suppress association with say "pro-life", or Christian based groups - it becomes precedent to suppress association across the board. They decry the lack of attendance in a Pride parade based on religious beliefs. People do not realize that it is not just
tolerance that is demanded, but a suspension of deeply held personal beliefs. I believe in the right to choose what is best for myself in regard to motherhood - and, I have chosen life. I made that decision with my husband, and family.