Today we cover d final bit of d #Process namely
#SCHEDULE which lists d #projects/activities for which #Prior #EC is mandatory.
#EIA1994 carried a list of 32 projects / activities that required environmental clearance (EC) from+
4.Materials Processing
5.Manufacturing / Fabrication
6.Service Sectors
7.Physical Infrastructure including Environmental Services
8.Building /Construction projects/Area Development projects and Townships
#CategoryA #projects/activities required #Prior #EC
“General Condition (GC):
Any project or activity specified in Category ‘B’ will be treated as Category 'A' (& hence require EC from GOI), if located in whole+
(i) Protected Areas notified under d Wild Life (Protection) Act, 1972
(ii) Critically Polluted areas as identified by d #CPCB frm time to time
(iii) Notified Eco-sensitive areas
(iv) inter-State boundaries & international boundary
In d "General Conditions" d previous distance of 10 km
Most problematic is d manner in which projects have been listed in #CategoryB2 with majority of them requiring no #EIA, #PublicConsultation or #appraisal & qualifying only for a diluted #EP (Environment Permission) from d #SEIAA.
No #EIAReport, #PublicConsultation or #Appraisal:
1. All projects of #Exploration for Offshore & Onshore
Oil & Gas (There can b serious env issues with such exploration?)
2. >25 MW hydro electric power generation (Micro hydel def changed?)
use & Heliports which r for commercial use. (Impacts on rivers & water bodies ignored?)
4. All projects in respect of Inland waterways (Impacts on rivers ignored?)
5. Expansion or widening of existing NH/Xpressways upto 100km & all SH
6. All Building & Construction projects upto 50,000 sq m built up area & upto 150,000 sq m built up area for 'Green certified', Industrial sheds, Educational Inst, Hospitals, & Hostels for students (Threshold+
7. Elevated roads, flyovers & Bridges with >150,000 sq m built up area (These have major env impacts?)