They looked at four workstreams that require new systems or infrastructure.
As of last month... *plans* were still being finalised...
"very little room for delay, and it carries significant risks"
A contract was awarded in May. Operational plans are still being drawn up...
There is 7 months to:
- Issue contract
- develop the system
- test it...
Currently done at 89 post offices, with about 100,000 issued annually.
Could be 4,500 post offices issuing up to 7 million permits.
They are yet to complete a business case or detailed plans.
There are no detailed delivery plans, not started on the new systems (necessary for Mar19 in no deal)... but still developing the project governance..