There is one particular kind of estimation I'd like to talk about today, backlog item estimation.
1/18
2/18
3/18
4/18
What might they be good for?
5/18
First, it can be useful to quickly go around the team and estimate a story, as a test of common understanding. If we all estimate pretty close to the same, we probably are all on board.
6/18
7/18
In my experience this is somewhat useful but fraught.
8/18
9/18
This is, in my view, almost certainly a Bad Idea.
10/18
11/18
12/18
13/18
14/18
15/18
16/18
In addition, they are often actively harmful. Again, they should be eliminated.
17/18
18/18