Dude borrowed N10m frm d bank to build an LPG plant
Plant ws built, ready for commissioning
Then like ants, more than 7 govt agencies came swooping in at the site & sealed it up
The total bribe demanded to re-open the gas plant is 12m
Invest in Nig? GOD FORBID
Survey,
CAC docs
Tax clearance
Location map
Police report
Fire Report
Town planning Approval drawings
EIA report
PI&D
Safety codes & Standards
Site layout
Dude said he has been on this for 1 1/2yrs with about 1.5m paid
No definite timeframe, useless bureaucracy, more money being requested, & bank loan interest & time of payment ticking, yet he hasn't started
So he took d law into hs hands & completed d plant pending wen d docs will be releasd
Gbam. Sealed up
You have to pay for them to inspect your site. Pay the other relevant govt agencies their own too, influence the results, pay up collect
1 1/2yr to process simple papers with 1.5m already paid from a loan within double digit interests? Common