With possession granted after close of service last night, work got underway to remove and replace bridge deck on #BonhillRd #Dumbarton.

Work is being delivered during 54hr closure of the line today and tomorrow.
Among the first tasks was to stone the road to level off camber underneth the structure to allow bridge transporter access to take weight of bridge deck - which has been pre cut.

We have also cleared the cables at track level to enable removal of deck #BonhillRd #Dumbarton
With the bridge transporter in position, it takes the weight of the deck and raises it circa 150mm to enable safe removal.

Also what it looks like from track level.

Work continues... #BonhillRd. #Dumbarton
And it’s up.

And out.

And off to the compound.

#BonhillRd #Dumbarton
The d bridge deck at #BonhillRd #Dumbarton heads off doon the road - passing the old signal box on its way.

Out with the old then it’s on to preparing for the new.
The existing abutments at #BonhillRd #Dumbarton are being cut down to fit the new cill units and deck.

Image shows abutment down to final cill level - ready to core and screed

Work continues...
Edge protection has been erected on the West & east side of bridge in advance of coring and screeding

Old deck being lifted from transporter to allow transporter to lift new deck and cills into position later. #BonhillRd #Dumbarton

Work continues...
In the early hours the new bridge deck with cils was lifted onto the transporter and driven from the compound to the site at #BonhillRd #Dumbarton

It was driven between the abutments and lowered precisely into. position

Work continues...
We are currently installing 4 transitions slabs by crane at #BonhillRd #Dumbarton

Once complete this will be followed by reinstatement of the ballast/track and reinstement of cabling across new deck

Work continues...
Progress continues with the fourth transition slab being craned in at #BonhillRd #Dumbarton. It’s busy at track level getting slabs properly positioned

Once completed the track team will get access to start the task of reinstating ballast sleepers and rails

Work continues...
Missing some Tweet in this thread?
You can try to force a refresh.

Like this thread? Get email updates or save it to PDF!

Subscribe to NetworkRail Scotland
Profile picture

Get real-time email alerts when new unrolls are available from this author!

This content may be removed anytime!

Twitter may remove this content at anytime, convert it as a PDF, save and print for later use!

Try unrolling a thread yourself!

how to unroll video

1) Follow Thread Reader App on Twitter so you can easily mention us!

2) Go to a Twitter thread (series of Tweets by the same owner) and mention us with a keyword "unroll" @threadreaderapp unroll

You can practice here first or read more on our help page!

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just three indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member and get exclusive features!

Premium member ($30.00/year)

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!