Work is being delivered during 54hr closure of the line today and tomorrow.
We have also cleared the cables at track level to enable removal of deck #BonhillRd #Dumbarton
Also what it looks like from track level.
Work continues... #BonhillRd. #Dumbarton
Out with the old then it’s on to preparing for the new.
Image shows abutment down to final cill level - ready to core and screed
Work continues...
Old deck being lifted from transporter to allow transporter to lift new deck and cills into position later. #BonhillRd #Dumbarton
Work continues...
It was driven between the abutments and lowered precisely into. position
Work continues...
Once complete this will be followed by reinstatement of the ballast/track and reinstement of cabling across new deck
Work continues...
Once completed the track team will get access to start the task of reinstating ballast sleepers and rails
Work continues...