Below is a list of 35 projects completed by the Transmission Company of Nigeria (TCN) in between 2016 and 2017. These new Power Transformers, and Mobile Substations have added more than 2,000 MW of new capacity to the national Grid.
#THREAD
1. 300MVA 330/132/33KV Power Transformers at Alagbon, Lagos state, added capacity-240MW (2016)
2. 300MVA 330/132/33KV Power Transformers at Lekki, Lagos state, added capacity-240MW (2016)
3. 150MVA 330/132//33KV Power Transformers at Kanji(fakun),Niger state, added capacity 120MW (2016)
4. 150MVA 330/132/33KV Power Transformers at Odukpani, Cross Rivers state, added capacity 120MW (2016)
5. 2x60MVA 132/33KV Power Transformers at Akagba, Lagos state, added capacity 96MW (2016)
6. 2x60MVA 132/33KV Power Transformer at Alagbon, Lagos state, added capacity 96MW (2016)
7. 2x60MVA 132/33KV Power Transformer at Lekki, Lagos state, added capacity 96MW (2016)
8. 2x60MVA 132/33KV Power Transformer at Agbor, Delta state, added capacity 96MW (2016)
9. 2x60MVA 132/33KV Power Transformer at Ihorvor, Delta state, added capacity 96MW (2016)
10. 2x60MVA 132/33KV Power Transformer at Lokoja, Kogi state, added capacity 96MW (2016)
11. 60MVA 132/33KV Power Transformer at Ughelli, Delta state, added capacity 48MW (2016)
12. 60MVA 132/33KV Power Transformers at kontagora, Niger state, added capacity 48MW 92016)
13. 60MVA 132/33KV Power Transformers at Isolo, Lagos state,added capacity 48MW (2016)
14. 60MVA 132/33KV Power Transformers at Okene, Kogi state, added capacity 48MW (2016)
15. 60MVA 132/33KV Power Transformers at Sokoto,Sokoto state, added capacity 48MW (2016)
16. 2x40MVA 132/33KV Power Transformer at Okada, Delta state, added capacity 64MW (2016)
17. 2x40MVA 132/33KV Power Transformer at Kainji(dogon gari), Niger state, added capacity 64MW (2016)
18. 300MVA 330/132/33KV Power Transformers at Ikeja west, Lagos , added capacity-240MW (2017)
19. 150MVA 330/132//33KV Power Transformers at Ayede, Oyo state, added capacity 120MW (2017)
20. 150MVA 330/132//33KV Power Transformers at Afam, River state, added capacity 120MW (2017)
21. 100MVA 132/33KV Power Transformer at Alimosho, Lagos state, added capacity 80MW (2017)
22. 2x60MVA 132/33KV Power Transformer at Kukuaba, FCT Abuja, added capacity 96MW (2017)
23. 60MVA 132/33KV Power Transformers at Ikorodu,Lagos state, added capacity 48MW (2017)
24. 60MVA 132/33KV Power Transformers at Ejigbo, Lagos state, added capacity 48MW (2017)
Missing some Tweet in this thread?
You can try to force a refresh.

Like this thread? Get email updates or save it to PDF!

Subscribe to Government of Nigeria
Profile picture

Get real-time email alerts when new unrolls are available from this author!

This content may be removed anytime!

Twitter may remove this content at anytime, convert it as a PDF, save and print for later use!

Try unrolling a thread yourself!

how to unroll video

1) Follow Thread Reader App on Twitter so you can easily mention us!

2) Go to a Twitter thread (series of Tweets by the same owner) and mention us with a keyword "unroll" @threadreaderapp unroll

You can practice here first or read more on our help page!

Did Thread Reader help you today?

Support us! We are indie developers!


This site is made by just three indie developers on a laptop doing marketing, support and development! Read more about the story.

Become a Premium Member and get exclusive features!

Premium member ($30.00/year)

Too expensive? Make a small donation by buying us coffee ($5) or help with server cost ($10)

Donate via Paypal Become our Patreon

Thank you for your support!