The wheeling capacity of TCN could be expanded by at least 2000MW by removing 132kV lines constraints.
#TCNPowerUpdate
TCN intends to re-conductor several 132kV transmission lines that has constrainted several substations using in-house capacity.
#TCNPowerUpdate
Meanwhile, some 330kV/132kV lines will be re-conductored using modern higher carrying capacity conductors.
#TCNPowerUpdate
The second phase of TREP that will expand and take the grid...
#TCNPowerUpdate
The 2nd Phase TREP will also provide the needed lines to evacuate the 3,050MW Mambila Hydro Electric Dam Project whose contract agreement was signed in 2017.
#TCNPowerUpdate
#TCNPowerUpdate
TCN intends to build new 330kV lines and associated substations to enable it effectively evacuate Mambila and create another transmission loop that will further strengthen the Grid and...
#TCNPowerUpdate
~ Calabar-Ikom-Ogoja-Mambilla 330kV DC line
~ Kano-Dutse-Azare-Potiskum – Damaturu 330kV DC Line
~ Damaturu-Biu-Gombi-Yola-Jalingo 330 DC Line and
~ Ajaokuta-Ayangba-Makurdi 330kV DC line.
#TCNPowerUpdate
* Ugwelli- Okpai 330kV Line
* Ugwelli-Port Harcourt 330kV DC line
* Sokoto-Katsina 330kV DC line and several 132kV DC lines and associated substations across the country.
#TCNPowerUpdate
#TCNPowerUpdate
Obviously, no Govt has dedicated on improving the Nigeria's power supply unlike what the president @MBuhari
administration has done so far. #TCNPowerUpdate