HIGHLIGHTS:
- Bridge now being funded from PIDF,which is overseen by NSIA
- NSIA has paid N33 Billion (US$90m) to J/Berger following signing of Main Works Agreement Aug 2018
#Thread
- 1.6km Bridge directly across River Niger
- 10.3km Highway connecting the Bridge on Onitsha & Asaba ends
J/Berger says Project now at 16% completion; will be completed by Feb 2022
PIDF will mobilize additional funding from private sector
DESIGN of the 10.3km Highway:
BRF (May 2018): "The design for the approach road that links Onitsha to the bridge and links Asaba to the bridge has now been completed; their was no design for it when we took office."
BRF: "We've received compensation claims of about N3.44 billion, that is a lot of money to pay for land, we've paid N1.8 billion [...] we keep receiving more claims and we want to be sure that we are paying the claims to the right people."
"We've received an additional claim of N1.5 billion, and almost everybody now seems to just be filing claims, these are some of the impediments... If we're paying N5bn towards compensation, how much will we spend towards the actual bridge itself?"