Whenever a customer makes a request to a Distribution Company for a new or additional connection to his premises, the Disco shall take measures to fit the meter and connect the power supply within ten (10) working days of receiving the request
a.The Disco shall inspect and approve the electrical installation
b.The Disco agrees to connect the supply
c.The customer has paid any approved charges
Every Distribution Company shall obtain, through authorized representatives an actual reading of all meters in all supply addresses within its area of supply every month but not later than once in every three (3) months.
Whenever a Disco is to discontinue the supply of a customers’ premises in order to undertake planned maintenance to its equipment, the Disco shall provide the customer with a minimum of three (3) workings days’ notice of planned interruption
When a customer reports a problem to a Disco that would suggest to the Disco that the cause of the problem is that the electricity used to record usage at the customers’ premises is recording incorrectly,
Whenever a customer whose premises have been disconnected by a Disco for non-payment of electricity charges either pays all outstanding charges including re connection charges,
Whenever a customer requests a Disco to re-position an electricity meter and pays the cost of carrying out the re-positioning, the Disco shall undertake work within five (5) working days of the request ;